Will Land Use Committee Evaluates Multi-Million Dollar Buyout for Flooded Harris Drive Homes

Spread the love

Will County Land Use & Development Committee Meeting | March 5, 2026

Article Summary: The Will County Land Use and Development Committee is exploring a multi-million-dollar buyout program for several homes in an unincorporated Joliet subdivision that is plagued by chronic flooding and failing septic systems.

Harris Drive Flooding Key Points:

  • A near-final engineering study by Baxter & Woodman suggests that purchasing and demolishing eight to nine homes is the only viable long-term solution to the neighborhood’s drainage crisis.

  • Total costs for appraisals, legal fees, acquisitions, relocation stipends, and demolition are expected to exceed $3 million.

  • The neighborhood sits near the DuPage River and suffers from a combination of surface runoff and high groundwater levels that overwhelm 1970s-era septic systems.

  • Because the area does not meet income qualifications for Community Development Block Grant (CDBG) funds, the county is actively hunting for competitive grant matches to fund the buyouts.

The Will County Land Use and Development Committee on Thursday, March 5, 2026, waded into a complex infrastructure crisis, reviewing a proposal to execute a multi-million-dollar buyout of heavily flooded homes on Harris Drive in unincorporated Joliet Township.

The discussion spilled over from the Public Health and Safety Committee meeting earlier in the day, where residents detailed how severe seasonal flooding and groundwater intrusion regularly disable their aging septic systems, leaving them unable to use their household plumbing for days or weeks at a time.

According to county Land Use staff, the county’s Stormwater Committee has been grappling with the Harris Drive flooding for over a year. The county recently hired engineering firm Baxter & Woodman to update a 15-year-old drainage analysis of the subdivision.

“What they’ve discovered is that because of the situation out there with the groundwater and the stormwater runoff, there’s probably about eight to nine homes that really just need to be purchased and the landowners need to be relocated,” a Land Use staff member explained to the committee. “Minor drainage improvements that the county could work to help get in place… are not going to be a big payback. They’re not going to help out the residents.”

Staff explained that simply putting in new ditches or grading the existing topography would not solve the core issue. Many of the homes, built around 1970, sit completely at grade—meaning their foundations are not elevated above the surrounding soil. When runoff flows from an adjacent uphill farm field, the water has nowhere to go but into the yards and homes, effectively drowning the septic leach fields.

Board members asked if the county could negotiate an intergovernmental agreement to hook the homes up to the City of Joliet’s municipal sewer and water systems. However, staff noted that because Harris Drive sits downhill from Joliet’s infrastructure, connecting the neighborhood would require the construction of an expensive lift station. Joliet officials previously indicated that such a project would also cost millions of dollars, require steep tap-on fees, and likely mandate annexation into the city.

With traditional engineering fixes ruled out, the county is looking at a massive real estate transaction.

“If you look at recent sales, each home is probably in the $250,000 to low $300,000 price [range],” staff noted. “You’ve got to have appraisals done, there’s engineering work, deeds have to be prepared, legal fees. Then you can’t just buy a home, you’ve got to help relocate the person… and then there’s demolition too.”

Because the neighborhood does not qualify as low-income, the county cannot tap into its standard Community Development Block Grant (CDBG) funds. Instead, the Stormwater Committee has identified roughly five competitive state and federal grants that could potentially fund the buyouts, though virtually all will require a substantial local funding match.

Staff cautioned that even if a grant is secured, the process mimics the county’s decade-long buyout efforts along the DuPage River and will require immense patience from residents.

“It’s not going to be immediate,” staff warned. “There’s no immediate fix because there’s not $3 million just available today to go out and take care of things like that.”

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 3.03.49 PM

Contracts Awarded for LED Signal Upgrades and Guardrail Maintenance

The Will County Public Works and Transportation Committee has approved contracts for two significant infrastructure maintenance projects: LED traffic signal upgrades and guardrail maintenance across the county. A contract for...
Screenshot 2025-05-04 at 3.03.49 PM

BRIEFS: Will County Public Works Projects

County Line Road Resurfacing Contract Awarded: The committee approved a $767,249 contract to Iroquois Paving Corporation for resurfacing County Highway 58 (County Line Road) from N5000 East Road east to...
Screenshot 2025-05-04 at 2.36.35 PM

County Approves Two Solar Energy Projects, Committee Discusses Zoning Challenges

The Will County Land Use and Development Committee approved two commercial solar energy projects Wednesday despite objections from the Village of Manhattan regarding one of the proposals. In a 6-1...
Screenshot 2025-05-04 at 2.36.35 PM

Committee Debates Easing Size Restrictions on Accessory Dwelling Units

Will County's Land Use and Development Committee is considering changes to its accessory dwelling unit (ADU) regulations that could provide more flexibility for homeowners looking to create additional living spaces...
Screenshot 2025-05-04 at 2.36.35 PM

“Tiny Homes” Status Creates Regulatory Confusion for County Officials

Will County officials are struggling to establish clear regulations for "tiny homes," with committee members expressing confusion over terminology and appropriate standards during Wednesday's Land Use and Development Committee meeting....
Screenshot 2025-05-04 at 2.36.35 PM

County Officials Begin Exploring Regulations for Small Modular Nuclear Reactors

Will County is beginning to explore potential regulations for small modular nuclear reactors (SMRs) after recent Illinois legislation allowed their development, planning staff told the Land Use and Development Committee...
Screenshot 2025-05-04 at 2.17.47 PM

Will County Land Use News Briefs

Truck Terminal Proposal Tabled for Traffic Study: The committee tabled a special use permit request from Litmax Multi-Service Inc. for a truck terminal in New Lenox Township at 22645 Cherry...
Screenshot 2025-05-04 at 2.57.14 PM

County Moves Forward with Veterans Building Renovations, Questions Arise on Pace Building Plans

Will County's Capital Improvements Committee received updates Tuesday on multiple county facility projects, including progress on the Copperfield Drive building renovations for veterans services, while discussions revealed questions about the...
Screenshot 2025-05-04 at 2.57.14 PM

County Continues Efforts to Reduce Leased Office Space Footprint

Will County officials reported Tuesday that efforts to consolidate county operations in owned facilities are continuing to reduce the county's leased office space footprint, with further reductions expected when the...
Screenshot 2025-05-04 at 2.57.14 PM

County Reports Significant Cost Savings Through In-House Facility Projects

Will County is achieving substantial cost savings by completing facility improvement projects with in-house staff rather than contracting the work out, according to a presentation to the Capital Improvements Committee...
Screenshot 2025-05-04 at 2.50.36 PM

County Legislative Committee Endorses Electronic Recycling Bill, Reviews Transit Governance

The Will County Legislative Committee voted Thursday to support proposed state legislation that would extend and expand Illinois' electronic recycling program, while also reviewing potential changes to regional transit governance...
Screenshot 2025-05-04 at 2.57.14 PM

Will County Capital Improvements News Briefs

Courthouse Scaffolding Expected to Come Down Soon: Scaffolding on one corner of the Will County Courthouse should be removed within the next two weeks, pending reports from material scientists. "We're...
Screenshot 2025-05-04 at 2.44.33 PM

County Finance Committee Advances Proposal for Elected Official Pay Raises After 20-Year Freeze

The Will County Finance Committee voted Thursday to advance a proposal that would provide the first salary increases for countywide elected officials and county board members in nearly two decades....
Screenshot 2025-05-04 at 2.50.36 PM

Will County Committee Debates Process for Taking Positions on State Legislation

Will County Legislative Committee members engaged in substantial discussion Thursday about how the committee should review and take positions on state legislation, with several members expressing concerns about the process...
Screenshot 2025-05-04 at 2.50.36 PM

State Lobbyists Update County on Springfield Action as Legislative Deadlines Approach

County officials received a comprehensive update on pending state legislation Thursday as lawmakers in Springfield approach critical deadlines for moving bills forward this session. Representatives from Mac Strategies, the county's...