Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Spread the love

Will County Public Works and Transportation Committee Meeting | March 3, 2026

Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to “D” Construction for a complete bridge replacement over Forked Creek.

Scheer Road Bridge Key Points:

  • The $1,596,116.16 contract was awarded to Coal City-based “D” Construction, Inc.

  • The project involves the removal of the existing bridge and construction of a new single-span concrete beam bridge.

  • The work on Scheer Road over Forked Creek is located in Green Garden Township (County Board Districts 2 and 3).

  • Construction will require a full roadway closure from April through September 2026.

The Will County Public Works and Transportation Committee on Tuesday, March 3, unanimously confirmed the award of a massive infrastructure contract to replace the aging Scheer Road bridge in Green Garden Township.

The $1,596,116.16 contract was awarded to “D” Construction, Inc., out of Coal City, which submitted the lowest qualified bid during the February 18 letting. The project will be funded through a combination of the Road District’s allotment of Motor Fuel Tax (MFT) funds and County Bridge Tax funds.

The comprehensive project (Section 21-07104-02-BR) will take place on Scheer Road over Forked Creek, impacting County Board Districts 2 and 3.

According to the project summary provided in the agenda packet, the scope of work consists of the complete removal of the existing bridge structure. In its place, crews will construct a new single-span concrete beam bridge. The project also entails installing new full-depth hot-mix asphalt pavement approaching the bridge, reconstructing the aggregate approach chip and seal north of the bridge, and adding new aggregate shoulders, guardrails, and riprap.

The road will be completely closed during the construction period. Work is estimated to begin in April 2026, with an estimated completion date of September 25, 2026.

The committee passed the resolution confirming the award without opposition.

Leave a Comment





Latest News Stories

will county board.3

Will County completes major projects while others move forward

Will County's facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday. The Old Courthouse Plaza...
will county board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will county board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will county board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will county board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
will county board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will county board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will county board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County Board Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will county board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will county board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will county board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will county board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
washington township graphic.1

Washington Township Approves $13,260 Security Overhaul, Opts for Local Vendor with 24/7 Service

Article Summary: The Washington Township Board of Trustees unanimously approved a $13,260 contract with TK Audio & Visual to comprehensively upgrade the security system at the Township Center. The final...
washington township graphic.2

Washington Township Board Appoints Teresa Peterson to Fill Vacancy

Article Summary: The Washington Township Board of Trustees is once again at full strength after unanimously appointing resident Teresa Peterson to fill a trustee vacancy. Peterson took the Oath of...