Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township
Will County Public Works and Transportation Committee Meeting | March 3, 2026
Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to “D” Construction for a complete bridge replacement over Forked Creek.
Scheer Road Bridge Key Points:
-
The $1,596,116.16 contract was awarded to Coal City-based “D” Construction, Inc.
-
The project involves the removal of the existing bridge and construction of a new single-span concrete beam bridge.
-
The work on Scheer Road over Forked Creek is located in Green Garden Township (County Board Districts 2 and 3).
-
Construction will require a full roadway closure from April through September 2026.
The Will County Public Works and Transportation Committee on Tuesday, March 3, unanimously confirmed the award of a massive infrastructure contract to replace the aging Scheer Road bridge in Green Garden Township.
The $1,596,116.16 contract was awarded to “D” Construction, Inc., out of Coal City, which submitted the lowest qualified bid during the February 18 letting. The project will be funded through a combination of the Road District’s allotment of Motor Fuel Tax (MFT) funds and County Bridge Tax funds.
The comprehensive project (Section 21-07104-02-BR) will take place on Scheer Road over Forked Creek, impacting County Board Districts 2 and 3.
According to the project summary provided in the agenda packet, the scope of work consists of the complete removal of the existing bridge structure. In its place, crews will construct a new single-span concrete beam bridge. The project also entails installing new full-depth hot-mix asphalt pavement approaching the bridge, reconstructing the aggregate approach chip and seal north of the bridge, and adding new aggregate shoulders, guardrails, and riprap.
The road will be completely closed during the construction period. Work is estimated to begin in April 2026, with an estimated completion date of September 25, 2026.
The committee passed the resolution confirming the award without opposition.
Latest News Stories
TrumpRx expanding, offering generic prescription drugs
Trump pauses planned military strikes against Iran, cites further negotiations
Tennessee AG leads 23-state letter over climate chapter in federal judges’ manual
Consumer advocates say Nicor’s rate hike is unreasonable, profit-driven
Dominion, NextEra plan merger
China to buy $17B in US ag products, 200 Boeing jets
Johnson’s office counters Pritzker claim Chicago mayor ‘has no plan’ to keep Bears
Minnesota prosecutor charges second ICE agent wake of Operation Metro Surge
Pritzker: Trump war to blame for high gas prices
Proposed law would require women’s restroom on construction sites
Republicans scramble to preserve White House ballroom security funding
CBP seizes more than 100 million lethal doses of fentanyl at SW border in six months