Beecher Board Awards $1.1 Million in Contracts for Miller Street Water Main Replacement

Spread the love

Village of Beecher Board of Trustees Meeting | March 23, 2026

Article Summary: The Village of Beecher has officially greenlit a massive summer infrastructure project, awarding nearly $1.1 million in construction and engineering contracts to replace the Miller Street water main. The project, which will stretch from Dixie Highway to Reed Street, will be heavily subsidized by a $500,000 grant from Will County.

Miller Street Water Main Key Points:

  • M&J Underground was awarded the base bid and option one for the construction project at a total cost of $994,957.74.

  • Baxter & Woodman was awarded a $92,000 contract for construction engineering after the board waived the formal bid process.

  • The Village is utilizing a $500,000 grant from the Will County ARPA Infrastructure Pillar Program to offset costs, with the remainder coming from the Water Main Replacement Fund.

  • Construction will target the 500, 600, and 700 blocks of Miller Street and will take place over the summer while school is out of session.

The Beecher Village Board on Monday, March 23, 2026, unanimously approved the financial framework for one of the village’s largest infrastructure upgrades of the year, formally awarding the contracts necessary to replace the aging Miller Street water main.

Following a competitive bidding process, the board voted 6-0 to award the base construction bid, along with “option one,” to M&J Underground for $994,957.74.

Public Works Committee Chair Erik Gardner outlined the project’s funding, noting that the village’s financial burden has been significantly reduced by outside subsidies. The village previously secured a $500,000 grant through Will County’s American Rescue Plan Act (ARPA) Infrastructure Pillar Program. The remaining balance of nearly $495,000 will be drawn from the village’s dedicated Water Main Replacement Fund.

In a separate but related 6-0 vote, the board agreed to waive the formal bidding process to hire Baxter & Woodman for the project’s construction engineering at a cost of $92,000.

To minimize disruption to the community, the village has scheduled the heavy construction to occur during the summer months.

“Just so that the public knows, the Miller Street water main project is all of Miller Street, the 500, 600, and 700 blocks of Miller from Dixie Highway all the way to Reed Street,” Gardner said. “It’ll be taking place this summer while the school is out of session.”

Leave a Comment





Latest News Stories

Screenshot 2025-10-17 at 2.37.04 PM

Beecher School Board Reviews Adding Accountability Clause to Oath of Office

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education held a first reading of a policy update that would add a formal...
solar panels photovoltaics in solar farm

Washington Township Asks Will County to Deny Beecher-Area Solar Farm

Washington Township Board Meeting | September 4, 2024 Article Summary: The Washington Township Board has formally stated its opposition to a proposed solar farm in Beecher's "backyard," sending a letter...
Screenshot 2025-10-17 at 2.36.52 PM

Beecher School District Invests Over $100,000 in New Bus and GPS System

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education approved the purchase of a new school bus for nearly $90,000 and a...
washington township graphic.2

Washington Township Board Approves Nearly $20,000 for New Digital Sign

Washington Township Board Meeting | September 4, 2024 Article Summary: The Washington Township Board has approved the purchase of a new, high-resolution LED message board for its highway sign at...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board for October 14, 2025

The Village of Beecher Board on Tuesday, October 14, 2025, heard a detailed proposal for a large-scale solar project in nearby unincorporated Will County that includes a $100,000 donation offer...
Screenshot 2025-10-17 at 2.36.39 PM

Facing Trainer Shortage, Beecher Schools to Use Paramedics for Athletic Coverage

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: In response to a shortage of available athletic trainers, the Beecher School District will partner with the Beecher...
washington township graphic.1

Washington Township Assessor Details New Veteran Tax Exemption, Rising Farmland Values

Washington Township Board Meeting | September 4, 2024 Article Summary: Washington Township Assessor Patricia Peters updated the board on a new state law that modifies the property tax exemption for...
Beecher Graphic.3

Annual Audit Affirms Beecher’s ‘Healthy Financial Position’

Article Summary: An independent audit of the Village of Beecher's finances for the fiscal year ending April 30, 2025, resulted in a clean opinion, with auditors confirming the village is...
Screenshot 2025-10-17 at 2.36.18 PM

Beecher School Board Approves Over $42,000 to Remediate Elementary School Tunnels

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education has approved a $42,645 contract with Allied Services to address long-standing moisture issues...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-10-16 at 8.18.26 PM

Beecher Board Considers $100,000 Offer Tied to Plum Valley Solar Project

Article Summary: A developer planning a 260-megawatt solar facility near Beecher has offered the village a $100,000 community benefit donation in exchange for a resolution of non-objection for the project....
Screenshot 2025-10-10 at 12.05.55 PM

Will County Board Committee Passes Contentious ‘Live and Work Without Fear’ Resolution on 4-3 Vote

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday narrowly passed a controversial resolution affirming the county's commitment to ensuring all residents...
Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million...
Screenshot 2025-10-10 at 12.12.16 PM

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for October 7, 2025

The Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a major construction contract and reviewed extensive plans for both county and state transportation initiatives. The...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for October 7, 2025

The Will County Finance Committee on Tuesday, October 7, 2025, held a contentious meeting centered on the county’s finances, narrowly approving a preliminary $161.6 million county-wide tax levy on a...