Article Summary: The Village of Beecher has officially greenlit a massive summer infrastructure project, awarding nearly $1.1 million in construction and engineering contracts to replace the Miller Street water main. The project, which will stretch from Dixie Highway to Reed Street, will be heavily subsidized by a $500,000 grant from Will County.

Miller Street Water Main Key Points:

  • M&J Underground was awarded the base bid and option one for the construction project at a total cost of $994,957.74.

  • Baxter & Woodman was awarded a $92,000 contract for construction engineering after the board waived the formal bid process.

  • The Village is utilizing a $500,000 grant from the Will County ARPA Infrastructure Pillar Program to offset costs, with the remainder coming from the Water Main Replacement Fund.

  • Construction will target the 500, 600, and 700 blocks of Miller Street and will take place over the summer while school is out of session.

The Beecher Village Board on Monday, March 23, 2026, unanimously approved the financial framework for one of the village’s largest infrastructure upgrades of the year, formally awarding the contracts necessary to replace the aging Miller Street water main.

Following a competitive bidding process, the board voted 6-0 to award the base construction bid, along with “option one,” to M&J Underground for $994,957.74.

Public Works Committee Chair Erik Gardner outlined the project’s funding, noting that the village’s financial burden has been significantly reduced by outside subsidies. The village previously secured a $500,000 grant through Will County’s American Rescue Plan Act (ARPA) Infrastructure Pillar Program. The remaining balance of nearly $495,000 will be drawn from the village’s dedicated Water Main Replacement Fund.

In a separate but related 6-0 vote, the board agreed to waive the formal bidding process to hire Baxter & Woodman for the project’s construction engineering at a cost of $92,000.

To minimize disruption to the community, the village has scheduled the heavy construction to occur during the summer months.

“Just so that the public knows, the Miller Street water main project is all of Miller Street, the 500, 600, and 700 blocks of Miller from Dixie Highway all the way to Reed Street,” Gardner said. “It’ll be taking place this summer while the school is out of session.”

Leave a Comment





Latest News Stories

House committee investigating Dem governors for 'illegal alien' Medicaid spending

House committee investigating Dem governors for ‘illegal alien’ Medicaid spending

By Sarah Roderick-Fitch | The Center SquareThe Center Square (The Center Square) – The House Committee on Oversight and Government Reform is launching an investigation into the “impact of the...
Illinois quick hits: House investigating Medicaid for illegal immigrants; transit concealed carry case decided by appeals court

Illinois quick hits: House investigating Medicaid for illegal immigrants; transit concealed carry case decided by appeals court

By Jim Talamonti | The Center SquareThe Center Square U.S. House investigating Medicaid for illegal immigrants A U.S. House committee is launching an investigation into Illinois and other states, seeking,...
WATCH: Chicago hearing addresses police workload; resident calls for federal help

WATCH: Chicago hearing addresses police workload; resident calls for federal help

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Chicago city council members did not discuss potential federal deployments during a public safety meeting Wednesday, but...
Arrest of Mexican national for 2023 murder called ‘long overdue’ justice

Arrest of Mexican national for 2023 murder called ‘long overdue’ justice

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Authorities confirmed the arrest of Gabriel Calixto in Mexico for the 2023 murder of Emma Shafer...
Meeting Briefs

Meeting Summary and Briefs: Beecher Board of Education for August 13, 2025

The Beecher Board of Education's regular meeting on Wednesday was highlighted by a detailed report from Superintendent Dr. Jack Gaham regarding the discovery and remediation of mildew in several classrooms...
Meeting-Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for August 25, 2025

The Beecher Village Board faced a crowd of frustrated residents during its Monday meeting, with the public comment session dominated by complaints about a residential construction site at 282 Orchard...
beecher ilinois school board graphic.3

Beecher School Board Tables $14,000 High School Window Graphics Project

Article Summary: The Beecher School Board on Wednesday postponed a decision on a more than $14,000 proposal to install decorative perforated vinyl graphics on the high school's front windows, citing...
Beecher Graphic.5

Beecher Board Sets New Rules for Electric Scooters, Opens Ponds to Fishing

Article Summary: The Beecher Village Board passed two ordinances creating new local regulations for low-speed electric scooters and officially permitting catch-and-release fishing in designated village-owned ponds. The scooter rules establish...
Trump says appeals court ruling rejecting tariffs 'highly partisan'

Trump says appeals court ruling rejecting tariffs ‘highly partisan’

By Brett RowlandThe Center Square President Donald Trump lashed out Friday night after a federal appeals court said he didn't have the power to issue the sweeping tariffs central to...
beecher ilinois school board graphic.5

Beecher School District Moves to Tier 2 State Funding, Finalizes Balanced Budget

Article Summary: Beecher School District 200-U has officially moved into Tier 2 of the state's Evidence-Based Funding model, a sign of improved financial health, Superintendent Dr. Jack Gaham announced Wednesday....
Beecher Graphic.3

Beecher Moves Forward with Miller Street Water Main Replacement Project

Article Summary: The Village of Beecher is restarting a major infrastructure project to replace the water main on Miller Street, approving a $23,000 contract with Baxter & Woodman to finalize...
DOJ urges federal judge to strike down climate change law

DOJ urges federal judge to strike down climate change law

By Chris WadeThe Center Square The Trump administration is asking a federal judge to invalidate a New York law that seeks to punish fossil fuel companies for their alleged role...
WATCH: Newsom deploys state police to help local law enforcement

WATCH: Newsom deploys state police to help local law enforcement

By Dave MasonThe Center Square New California Highway Patrol teams will work with local law enforcement to fight crime in Los Angeles, San Diego, Sacramento, the San Francisco Bay Area,...
Appeals court rejects Trump's tariffs, but leaves them in place

Appeals court rejects Trump’s tariffs, but leaves them in place

By Brett RowlandThe Center Square A federal appeals court said Friday that President Donald Trump doesn't have the authority to issue blanket tariffs, in a blow to the president's domestic...
Denver Public Schools accused of violating Title IX

Denver Public Schools accused of violating Title IX

By Esther WickhamThe Center Square The U.S. Department of Education for Civil Rights announced this week that Denver Public Schools' policies on “all-gender” facilities violate Title IX. The department's Office...