Article Summary: A 52-acre commercial solar energy facility in Peotone was approved by the Will County Board despite concerns raised by members regarding the use of local union labor and the vulnerability of solar panels to severe weather.

Peotone Solar Farm Key Points:

  • The board approved Ordinance #26-063 for a special use permit for a 4.98-megawatt solar facility at 5949 W. Eagle Lake Road in Peotone.

  • Developer BAP Power assured the board that it utilizes union labor, anticipating new state laws requiring triparty labor agreements starting in June.

  • Board members debated the safety of solar farms following recent tornadoes, with conflicting reports on the extent of damage to existing arrays.

  • The board also approved extensions for previously permitted solar farms in Peotone, Monee, and Joliet townships.

The Will County Board on Thursday, March 19, 2026, granted a special use permit for a new commercial solar farm in Peotone, though the approval sparked extensive debate regarding labor practices and storm resiliency.

The board voted 14-1 to approve Ordinance #26-063, granting a special use permit for a commercial solar energy facility on 52.65 acres located at 5949 W. Eagle Lake Road in Peotone (Will Township). The applicant, BAP Power (doing business as Cenergy Power), plans to construct a 4.98-megawatt ground-mounted solar photovoltaic system.

Prior to the vote, Member David G. Oxley requested that the developer address the board regarding their hiring practices.

“The question is, what percentage of local labor will be used on this project?” Oxley asked.

Chad Chabazi, representing BAP Power, stated that while he did not have an exact percentage, the company tries to use as much local union labor as possible. He also noted that under the state’s new Climate and Equitable Jobs Act (CEJA) rules, which go into effect on June 1, 2026, any project over three megawatts receiving a renewable energy contract from the state will be legally required to have a triparty labor agreement.

“Pretty much all the work that we do on these sites are union labor,” Chabazi said.

Member Frankie Pretzel noted that the board frequently receives letters from local unions, such as the Carpenters Union Local 174, asking the county to ensure these projects employ local workers.

“I don’t love these solar projects when we have people from the community coming and saying I don’t want this,” Pretzel said. “What I do love about these is that it can create local jobs… I just wish that we could condition these requests somehow to say that they have to use local unions to do the work.”

Assistant State’s Attorney Kevin Meyers advised the board that under current state law, the county does not have the legal authority to mandate a project labor agreement as a condition of a special use permit.

Safety concerns were also raised regarding the physical durability of solar farms. Member Judy Ogalla referenced a recent tornado that severely damaged a solar facility, noting that cleanup crews were seen wearing hazmat suits.

“I’d like to know more from land use as, you know, what’s the impact going to be if one of these gets destroyed here in an EF4 or EF5 [tornado]?” Ogalla asked.

Member Mica Freeman offered a different perspective, stating she recently drove past a large solar farm in Kankakee County that had been struck by a tornado.

“I can tell you that the houses across the street were in much worse damage than the solar panels that were on the ground,” Freeman said.

In addition to the new Peotone facility, the board approved several extensions for previously permitted solar farms, giving developers more time to secure building permits. These included Resolution #26-064 (SEXT-26-001) for Prairie Solar LLC on West Kennedy Road in Peotone Township, and Resolutions #26-069 (SEXT-26-006) and #26-070 (SEXT-26-007) for two Dralle Sun LLC facilities located on Dralle Road in Monee Township.

Beecher Weather Full forecast →
⚠️ Flood Watch issued June 10 at 6:54PM CDT until June 11 at 4:00AM CDT by NWS Chicago IL
Wed Jun 10
Partly Sunny then Slight Chance Showers And Thunderstorms
88° 60°

Partly Sunny then Slight Chance Showers And Thunderstorms

💨 10 to 20 mph 💧 15%

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Beecher Public Library District Board for August 19, 2025

The Beecher Public Library District Board of Trustees addressed major financial milestones and a significant leadership change at its August 19 meeting. The board unanimously approved the final budget for...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
washington township graphic.3

Failed Repair Forces Replacement of 25-Year-Old Furnace at Washington Township Center

Article Summary: A failed repair attempt on the 25-year-old furnace at the Washington Township Center, which caused a fire alarm to activate, has prompted the board to authorize a full...
OLYMPUS DIGITAL CAMERA

Beecher Library Board Approves Budgets for Current and Upcoming Fiscal Years

Article Summary: The Beecher Public Library District Board of Trustees formally approved its final budget for the current 2024-2025 fiscal year and, following a public hearing, passed the new budget...
Meeting Briefs

Meeting Summary and Briefs: Beecher School District 200-U for September 10, 2025

The Beecher School District 200-U Board of Education approved its annual budget, appointed a new member, and greenlit a cosmetic upgrade for the high school during its meeting on September...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for September 22, 2025

The Beecher Village Board addressed persistent structural issues at the new Public Safety Facility during its meeting on September 22. After a report confirmed that new roof leaks have appeared...
washington township graphic.1

Washington Township Overhauls Wage Structure, Boosts Bus Driver Pay

Article Summary: The Washington Township Board of Trustees has initiated a comprehensive review of its wage and job structures to align with state law, improve competitiveness for key positions like...
beecher illinois public library graphic.1

Beecher Library Board President Shirley Biery Announces Resignation

Article Summary: Shirley Biery has announced she will resign from her position as President and Trustee of the Beecher Public Library District Board, effective August 31, 2025. Following the announcement...
Screenshot 2025-09-23 at 7.57.19 PM

Beecher Creates New Adjudication Clerk Position to Manage Municipal Court

Article Summary: The Village of Beecher has formally created the position of Adjudication Clerk by amending its municipal code, aiming to streamline the management of its local ordinance violation hearings....
Screenshot 2025-09-23 at 8.04.29 PM

Beecher High School to Get New Look with Approved Window Wrap

Article Summary: Beecher High School is set for an aesthetic upgrade after the Board of Education approved a nearly $12,500 proposal for a decorative and security-enhancing window wrap. After some...
Screenshot 2025-09-23 at 7.55.43 PM

State’s Attorney Donates Tint Meters to Beecher Police to Enhance Traffic Safety

Article Summary: The Beecher Police Department has received 14 new window tint meters through a donation from the Will County State's Attorney's Office. State's Attorney Jim Glasgow personally presented the...