Will County Board Meeting | March 19, 2026

Article Summary: The Will County Board approved a series of heavy infrastructure contracts, highlighted by a nearly $1.6 million bridge replacement in Green Garden Township and a $959,000 roadway improvement project in New Lenox.

Public Works Contracts Key Points:

  • “D” Construction, Inc. was awarded a $1,596,116.16 contract to replace the Scheer Road bridge over Forked Creek in Green Garden Township.

  • Northern Builders was awarded a $959,625 agreement for roadway improvements on Laraway Road in New Lenox to facilitate a new commercial warehousing development.

  • The board approved several land acquisition agreements for the ongoing widening of Weber Road and Gougar Road.

  • Northern Contracting, Inc. received a $317,671 contract for countywide guardrail maintenance.

The Will County Board on Thursday, March 19, 2026, greenlit a multi-million-dollar slate of public works contracts aimed at upgrading rural bridges, accommodating industrial growth, and maintaining existing infrastructure across the county.

Operating through its consent agenda, the board unanimously approved Resolution #26-078, awarding a contract to Coal City-based “D” Construction, Inc. at a total cost of $1,596,116.16. The project entails the complete removal of the existing bridge on Scheer Road over Forked Creek in Green Garden Township. Crews will construct a new single-span concrete beam bridge, install new full-depth hot-mix asphalt pavement approaching the bridge, and reconstruct the aggregate shoulders and guardrails. The project is funded through the Road District’s allotment of Motor Fuel Tax funds and County Bridge Tax funds.

The board also approved Resolution #26-084, authorizing a construction agreement with Northern Builders for improvements on Laraway Road from Cherry Hill Road to Nelson Road in New Lenox. The $959,625 project will widen the existing two-lane roadway to a four-lane roadway with a center barrier median to accommodate a new commercial warehousing development. The improvements will also include modernization of traffic signals at the intersection of Gougar Road.

In preparation for future road expansions, the board authorized several professional services agreements for right-of-way acquisitions. This included Resolution #26-079, a $353,650 contract with Hampton, Lenzini and Renwick, Inc. to secure appraisals and negotiations for 43 parcels along Weber Road from Airport Road to 135th Street.

Additionally, the board approved Resolution #26-076, awarding a $317,671 contract to Northern Contracting, Inc. for countywide guardrail maintenance, funded via Motor Fuel Tax funds.

Leave a Comment





Latest News Stories

Meeting-Briefs

Committee Summary and Briefs: Peotone Board of Education Committee of the Whole

The Peotone School District 207-U is on a collision course with a major financial crisis, which dominated the Board of Education’s committee meeting on August 18. Facing a projected $4.2...
Soaring utility bills, solar federal tax credit cuts dominate Illinois energy debate

Soaring utility bills, solar federal tax credit cuts dominate Illinois energy debate

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Energy prices and clean energy policy took center stage during a senate energy and public utilities...

Illinois quick hits: Pritzker signs crypto regulations

By Jim Talamonti | The Center SquareThe Center Square Pritzker signs crypto regulations Gov. J.B. Pritzker has signed two laws to regulate cryptocurrency. Senate Bill 1797 requires cryptocurrency companies to...
Trucking industry leader: New law may drive business out of Illinois

Trucking industry leader: New law may drive business out of Illinois

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A trucking industry leader says more businesses may leave Illinois after the signing of Senate Bill 328....
Exec Cmte 8.14.25.3

Executive Committee Considers $12,000 Strategic Planning Initiative with University of St. Francis

Article Summary: The Will County Executive Committee is considering a proposal from the University of St. Francis to lead a six-month, $12,178 strategic planning process. The initiative is aimed at...
Exec Cmte 8.14.25.2

Executive Committee Members Decry Roadside Litter, Call for Action Against Garbage Haulers

Article Summary: Will County Executive Committee members expressed frustration over what they described as a worsening problem of litter blowing from garbage trucks across the county. Members called for better...
Ad Hoc.8.12.25.3

Will County Updates Solid Waste Ordinance, Increases Fines and Reporting to Landfill Committee

Article Summary: The Will County Ad-Hoc Ordinance Review Committee advanced an updated solid waste ordinance that doubles the maximum fine for violations and requires the county auditor's annual report to...
Ad Hoc.8.12.25.2

Citing Liability Concerns, Will County Committee Postpones Vote on Septic System Ordinance

Article Summary: The Will County Ad-Hoc Ordinance Review Committee postponed a vote on updating its sewer and sewage disposal ordinance after a member raised significant concerns about the county's liability...
Ad Hoc.8.12.25.1

Will County Moves to Repeal Obsolete 1972 Fire Hydrant Ordinance

Article Summary: An ordinance from 1972 regulating the placement and specifications of fire hydrants in Will County is set to be repealed after the Ad-Hoc Ordinance Review Committee approved its...
Committee of teh Whole 8.12.25

Will County Board Gets Back to Basics with Robert’s Rules of Order Training

Article Summary: The Will County Board Committee of the Whole received a detailed training session on Robert's Rules of Order from parliamentary expert Matthew Prochaska to clarify procedures for conducting...
Exec Cmte 8.14.25.1

Executive Committee Approves Amended Houbolt Bridge Agreement to Settle Litigation

Article Summary: The Will County Executive Committee has approved an amendment to the Houbolt Road Toll Bridge agreement, formalizing a settlement between the bridge operators and the City of Joliet....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Committee of the Whole for August 12, 2025

The Will County Board’s Committee of the Whole dedicated its August 12 meeting to an in-depth training session on Robert’s Rules of Order, aiming to foster more efficient and orderly...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for August 12, 2025

The Will County Ad-Hoc Ordinance Review Committee advanced several updated chapters of the county’s public works code during its August 12 meeting, addressing topics from solid waste to waste hauler...
WCO Landfill 8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary: The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on...
WCO Landfill 8.5.25.2

Report Finding Few Trucks Littering Sparks Debate on Cleanup Responsibility

Article Summary: A Will County report found that a very small percentage of waste-hauling trucks are the source of litter on roadways near the county landfill, sparking a debate among...