Will County Capital Improvements & IT Committee Meeting | April 7, 2026

Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county government facilities in downtown Joliet, including a potential partnership to build a joint complex with the City of Joliet. Financial advisors also presented bonding scenarios that could fund up to $142.8 million in construction without raising the county’s current annual debt service.

Facilities Master Plan Key Points:

  • Space projections indicate the County Office Building needs to grow from its current 62,260 square feet to 118,000 square feet by 2050.

  • Wight & Company presented four consolidation options for downtown Joliet, ranging from a standalone county facility on the old courthouse site to a “mega consolidation” housing both county and city government.

  • City of Joliet City Manager Beth Beatty addressed the committee, expressing strong support for a joint “one-stop shop” facility.

  • Speer Financial presented three borrowing scenarios, showing the county could issue between $103.9 million and $142.8 million in new bonds while maintaining its targeted $25 million annual debt service.

  • The county currently leases the “PACE building” at 9 Osgood Street to the City of Joliet for $1 a year on a 99-year lease.

The Will County Board Capital Improvements & IT Committee on Tuesday, April 7, 2026, took its first major step toward a massive overhaul of its downtown Joliet footprint, reviewing four architectural consolidation scenarios that could fundamentally reshape local government operations.

Jason Dwire of Wight & Company presented the updated Facilities Master Plan, highlighting the urgent need to replace or expand the current County Office Building (COB) and the MCO Building, which currently houses the State’s Attorney and Probation departments. According to the data, the county’s core government functions currently occupy 62,260 square feet but will require 118,000 square feet by 2050.

“This building here, it doesn’t really accommodate all of the county government functions,” Dwire said, referencing a map showing county offices scattered across downtown. “It certainly doesn’t meet any of the projected needs going forward. The same is true in the MCO building… Both buildings are going to need significant continued investment to maintain them, and they’re not in the best layout or best shape to begin with.”

Dwire outlined four distinct options for the committee, all of which heavily utilize the site of the now-demolished old courthouse:

  • Option 1: Consolidate all county government functions into a new 164,100-square-foot building on the old courthouse site. A separate Judicial Annex and parking garage (260,700 sq. ft.) would be built south of the new courthouse for the State’s Attorney and Public Defender.

  • Option 2: Build a joint 247,100-square-foot facility on the old courthouse site housing both Will County Government and the City of Joliet. A 269,800-square-foot Judicial Annex would be built south of the new courthouse.

  • Option 3: Consolidate all county needs—including the State’s Attorney and Public Defender—into one massive 277,200-square-foot building. This would allow the county to abandon the MCO site entirely, potentially offering it to the City of Joliet for a new City Hall (estimated 82,400 sq. ft.).

  • Option 4: A “mega consolidation” placing Will County Government, Judicial Agency Offices, and the City of Joliet into a single 385,600-square-foot complex on the old courthouse site, accompanied by a 230,400-square-foot parking garage.

The prospect of a joint county-city complex drew significant interest from the committee and the City of Joliet. Joliet City Manager Beth Beatty attended the meeting to confirm the city’s willingness to partner.

“The council, the mayor, and I… we have a wonderful working relationship with the county, and we are struggling just as you are with our city hall. I don’t have enough places to put people that we’re hiring now,” Beatty said. “We love the idea of a combined building with the county, so it’s a one-stop shop for constituents.”

Mike Mahony, speaking on behalf of the county executive’s office, noted that a joint facility would offer massive economies of scale, from sharing a single HVAC system and security entrance to utilizing a shared civic boardroom for both County Board and City Council meetings.

To fund such a monumental project, the committee reviewed a debt update prepared by Anthony Miceli of Speer Financial. Following a highly successful bond refinancing in October 2025 that saved the county $5,739,302.60, the county’s debt service payments are positioned to drop off significantly after 2031.

Assuming the issuance of 20-year General Obligation (Alternate Revenue Source) bonds, Speer Financial provided three scenarios that would allow the county to fund construction while keeping its overall annual debt payments level at a targeted $25 million:

  • Scenario 1: A single 20-year issuance in 2027 generating $103,995,000.

  • Scenario 2: A two-part issuance in 2027 and 2030 generating a combined $131,415,000.

  • Scenario 3: A three-part issuance in 2027, 2029, and late 2030 generating $142,810,000.

“You have space and capability to bond out,” Mahony explained. “These are all hypothetical scenarios. We don’t know if we are going to do anything. We don’t know what option we will be looking at… this was just to give you an idea that there is debt service capability for the county that would pay for a project of this magnitude.”

Board Member Steve Balich (R-Homer Glen) suggested an alternative to new construction: expanding the county-owned “PACE building” at 9 Osgood Street.

Mahony countered that the building is currently leased to the City of Joliet for $1 a year on a 99-year lease—an exchange that saved the county nearly $100,000 annually in lease space for problem-solving courts. Furthermore, Mahony noted the building features a 1950s wood roof structure and houses vehicle maintenance on the first floor, making vertical expansion highly problematic due to structural integrity, emissions, and noise.

Despite the logistical hurdles, Balich requested that Wight & Company officially review the PACE building’s expansion feasibility, a request the committee honored.

Board Member David G. Oxley (R-Lockport) requested a comprehensive breakdown of the county’s current lease costs versus the projected savings of consolidation. Mahony noted that the county has aggressively reduced its leased footprint recently—moving the Veterans Assistance Commission and Workforce Services into owned buildings—leaving only Land Use, the Public Defender, and a small ~500-square-foot office for the Workforce Investment Board in leased spaces.

No final decisions were made, as the committee directed staff to return next month with refined cost estimates for the various architectural options.

Leave a Comment





Latest News Stories

Pennsylvania lawmakers criticize violent ICE encounters

Pennsylvania lawmakers criticize violent ICE encounters

By Christina LengyelThe Center Square With ongoing protests across the commonwealth over the actions of the Department of Homeland Security’s Immigration and Customs Enforcement, or ICE, 18 Pennsylvania legislators have...
WATCH: Tax increase talk at Statehouse; Bost’s election lawsuit against Illinois wins standing

WATCH: Tax increase talk at Statehouse; Bost’s election lawsuit against Illinois wins standing

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop discusses the status of...
Illinois Quick Hits: Indiana governor 'working hard' to attract Bears

Illinois Quick Hits: Indiana governor ‘working hard’ to attract Bears

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Indiana Gov. Mike Braun says the Chicago Bears noticed that the Hoosier state is open for business....
Will County Logo Graphic

Meeting Summary and Briefs: Capital Improvements & IT Committee for January 6, 2026

Capital Improvements & IT Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Capital Improvements and IT Committee met on Tuesday, January 6, 2026, to discuss facility...
Beecher Graphic.1

Public Works Shifts Focus to Snow Removal; Spring Leaf Collection Promised

Village of Beecher Board Meeting | January 12, 2026 Article Summary: Public Works Superintendent Matt Conner informed the board that crews are finishing the final leaf collection of the season...
Will County Board Graphic.04

Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for January 7, 2026

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Overall Meeting SummaryThe Will County Board Public Health and Safety Committee met on Wednesday, January 7, 2026,...
Beecher Graphic.5

Beecher Village Board Appoints New Clerk, Approves Environmental Justice Committee Role

By : Andrea Arens The Village of Beecher Board of Trustees kicked off the new year at its January 12 meeting with several key decisions, including the appointment of a...
Vance's tie-breaking vote tanks resolution restricting Venezuela military actions

Vance’s tie-breaking vote tanks resolution restricting Venezuela military actions

By Thérèse BoudreauxThe Center Square By the slimmest of margins, the U.S. Senate successfully derailed a resolution that would have curtailed the Trump administration’s power to continue military action in...
Federal court upholds California congressional redistricting

Federal court upholds California congressional redistricting

By Dave MasonThe Center Square California’s congressional redistricting, designed to pick up five more Democratic seats in this year’s midterm elections, was upheld Wednesday in a federal court in downtown...
Trump orders new mediation for New York rail contract dispute

Trump orders new mediation for New York rail contract dispute

By Chris Wade contributionThe Center Square President Donald Trump on Wednesday ordered new mediation for stalled contract talks between New York's Metropolitan Transportation Authority and union leaders in a last-ditch...
U.S. House passes two more govt funding bills, sending to Senate

U.S. House passes two more govt funding bills, sending to Senate

By Thérèse BoudreauxThe Center Square In a bipartisan vote Wednesday, the U.S. House passed a minibus containing two more full-year federal funding bills, sending the package to the Senate for...
Governors seek delay on sharing cost of food stamp errors

Governors seek delay on sharing cost of food stamp errors

By Brett RowlandThe Center Square State and local officials are asking Congress for a delay on sharing the cost of errors in the federal food assistance program, but said they...
Supreme Court ruling allows Bost to challenge Illinois election law

Supreme Court ruling allows Bost to challenge Illinois election law

By Catrina Baker | The Center Square contributorThe Center Square (The Center Square) – A U.S. Supreme Court ruling clears the way for U.S. Rep. Mike Bost to challenge Illinois’...
Illinois quick hits: Illinois auto insurance rates dropping

Illinois quick hits: Illinois auto insurance rates dropping

By Jim Talamonti | The Center SquareThe Center Square Illinois auto insurance rates dropping A new report says Illinois auto insurers are lowering premiums by 4.26% in 2026 while providers...