Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities that will serve both a new residential subdivision and the upcoming Laraway Road widening project.

Laraway Road / LNS Development Key Points:

  • Will County and LNS Development Group, LLC will co-fund shared stormwater infrastructure.

  • The county will pay an estimated $332,209.92 for its share of the detention facility and storm sewer upgrades.

  • The county is also paying LNS Development $19,862.03 to acquire 0.43 acres of right-of-way required for the Laraway Road widening project.

  • The Laraway Road project will widen the highway to four lanes between Cedar Road and Spencer Road.

Will County is leveraging private development to streamline its own infrastructure costs, approving an agreement with LNS Development Group, LLC on Tuesday, April 7, 2026, to construct shared stormwater facilities along Laraway Road in New Lenox.

The agreement centers on a parcel of land (PIN 15-08-35-100-011) where LNS Development is planning a new residential subdivision. Concurrently, Will County is engineering a major capacity project to widen Laraway Road (County Highway 74) from a two-lane road to a four-lane highway with a center barrier median from Cedar Road to Spencer Road.

Because both the county’s highway expansion and the private residential development require significant stormwater management, the two entities agreed to co-locate and share the costs of a detention facility and upgraded storm sewers on the developer’s parcel.

According to the engineer’s estimates provided in the agenda packet, Will County’s financial obligation for the construction of the shared improvements is capped at an estimated $332,209.92. This breaks down to $179,218.92 (21% of the total cost) for the detention basin, and $152,991.00 (100% of the required upgrades) to properly size the storm sewers to accommodate WCDOT drainage. LNS Development will cover the remaining construction costs.

Furthermore, the agreement secures the land Will County needs to physically widen the road. LNS Development will convey 0.43668 acres of right-of-way to the county in exchange for $19,862.03. In return, the county guarantees the developer’s vested rights to specific access points and drainage capacity along the newly widened highway.

The measure was passed unanimously and advances to the full County Board.

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 2.57.14 PM

County Reports Significant Cost Savings Through In-House Facility Projects

Will County is achieving substantial cost savings by completing facility improvement projects with in-house staff rather than contracting the work out, according to a presentation to the Capital Improvements Committee...
Screenshot 2025-05-04 at 2.50.36 PM

County Legislative Committee Endorses Electronic Recycling Bill, Reviews Transit Governance

The Will County Legislative Committee voted Thursday to support proposed state legislation that would extend and expand Illinois' electronic recycling program, while also reviewing potential changes to regional transit governance...
Screenshot 2025-05-04 at 2.57.14 PM

Will County Capital Improvements News Briefs

Courthouse Scaffolding Expected to Come Down Soon: Scaffolding on one corner of the Will County Courthouse should be removed within the next two weeks, pending reports from material scientists. "We're...
Screenshot 2025-05-04 at 2.44.33 PM

County Finance Committee Advances Proposal for Elected Official Pay Raises After 20-Year Freeze

The Will County Finance Committee voted Thursday to advance a proposal that would provide the first salary increases for countywide elected officials and county board members in nearly two decades....
Screenshot 2025-05-04 at 2.50.36 PM

Will County Committee Debates Process for Taking Positions on State Legislation

Will County Legislative Committee members engaged in substantial discussion Thursday about how the committee should review and take positions on state legislation, with several members expressing concerns about the process...
Screenshot 2025-05-04 at 2.50.36 PM

State Lobbyists Update County on Springfield Action as Legislative Deadlines Approach

County officials received a comprehensive update on pending state legislation Thursday as lawmakers in Springfield approach critical deadlines for moving bills forward this session. Representatives from Mac Strategies, the county's...
Screenshot 2025-05-04 at 2.50.36 PM

Will County Legislative Committee News Briefs

Committee Postpones Action on Felony Conviction Voting Rights Bill: The Will County Legislative Committee declined to support House Bill 1288, which would allow individuals convicted of felonies to run for...
Screenshot 2025-05-04 at 2.44.33 PM

Shanahan Development Agreements Near Completion, Will County to See $282,000 Annual Revenue Boost

Will County will soon begin receiving the full tax benefit from industrial developments in Shanahan as the tax abatement and rebate agreements that helped fund infrastructure improvements approach their completion...
Screenshot 2025-05-04 at 2.44.33 PM

County Explores Bond Refinancing Options to Generate Potential Savings

Will County officials are exploring opportunities to refinance existing debt that could generate significant savings through two separate financial strategies, according to presentations to the Finance Committee on Thursday. Financial...
Screenshot 2025-05-04 at 2.44.33 PM

County Approves $150,000 for Medicare/Medicaid Billing Consultant for Health Department, Nursing Home

Will County will hire a consultant to review Medicare and Medicaid billing practices at both the county health department and Sunny Hill Nursing Home, aiming to maximize reimbursements and address...
Screenshot 2025-05-04 at 2.44.33 PM

County Receives First $50,000 Administrative Fee from Joliet Arsenal Enterprise Zone

Will County will collect its first $50,000 administrative fee from a business utilizing the Joliet Arsenal Enterprise Zone, after the Finance Committee approved appropriating the payment to the Land Use...
Screenshot 2025-05-04 at 2.44.33 PM

Will County Finance Committee News Briefs

County Property Tax Base Grows to $30.5 Billion: The county's net equalized assessed value (EAV) for the 2025 fiscal year reached $30.5 billion, finance officials reported during discussion of final...