Will County Board Graphic.03

Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Beecher Weather Full forecast →
⚠️ Flood Watch issued June 10 at 9:11PM CDT until June 11 at 4:00AM CDT by NWS Chicago IL
Wed Jun 10
Partly Sunny then Slight Chance Showers And Thunderstorms
88° 60°

Partly Sunny then Slight Chance Showers And Thunderstorms

💨 10 to 20 mph 💧 15%

Leave a Comment





Latest News Stories

Committee-Land Use.Graphic

Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026

Will County Land Use & Development Committee Meeting | February 5, 2026 The Will County Land Use and Development Committee met on Thursday, February 5, 2026, to deliberate on several...
Beecher Graphic.1

Beecher Village Board Splits on Capital Spending: Park Stage Renovation Rejected, Police Sign Approved

Village of Beecher Board Meeting | Feb 23, 2026 Article Summary: The Beecher Village Board engaged in a debate over how to allocate nearly $227,000 in proceeds from the sale...
Committee-Executive.Graphic

Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026

Will County Executive Committee Meeting | February 11, 2026 Meeting SummaryThe Will County Board Executive Committee met on Wednesday, February 11, 2026, tackling a heavy agenda focused on economic development...
Election Vote Graphic

Group Presents Allegations of 2024 Voter Roll Errors to County Board

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a resolution calling for the review of election systems and integrity, following public comments alleging inaccuracies...
beecher illinois public library graphic.1

Library Moves Forward with Entrance Project, Faces Heating System Failure

Beecher Public Library District Meeting | Jan. 20, 2026 Article Summary: The Beecher Public Library District Board set the timeline for bidding on its main front entrance project and addressed...
Will County Board Graphic.04

Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: During a detailed legal briefing on Tuesday, the Will County Landfill Committee received strict instructions regarding their conduct during...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Bath House Regulations Updated; Removes 60-Day Licensing Window

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to the regulations governing bath houses and...
Committee-Land Use.Graphic

Land Use Committee Rejects Shorewood Solar Farm Despite 25-Year Lease Offer

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use and Development Committee voted against recommending a controversial solar farm proposal...
Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in...
Committee-Land Use.Graphic

Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: A request to rezone land for a "clean fill" operation in Joliet Township stalled in committee...
Committee-Planning & Zoning.Graphic

Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026

Will County Planning and Zoning Commission Meeting | February 17, 2026 JOLIET, IL – The Will County Planning and Zoning Commission met on Tuesday, February 17, 2026, with Acting Chairman John...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Liquor Ordinance Stalls Over Drafting Errors; Debates License Cap Policy

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee postponed a vote on the comprehensive update to the...
Committee-Executive.Graphic

Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm

Will County Executive Committee Meeting | February 11, 2026 Article Summary: Residents of Green Garden Township warned county officials they are moving to incorporate as a village to gain zoning...
Meeting Briefs

Meeting Summary and Briefs: Beecher Board of Education for February 11, 2026

Beecher Board of Education Meeting | February 11, 2026 The Beecher Board of Education met on Wednesday, February 11, 2026, to review academic data and approve several operational contracts. The...
Elsie's Place, located at 1140 Dixie Highway, Unit 1, marked its official launch today with a grand opening and ribbon-cutting ceremony! Elsie's Place is a sandwhich shop with gaming.

Elsies Place Grand Opening

Elsie's Place, located at 1140 Dixie Highway, Unit 1, marked its official launch today with a grand opening and ribbon-cutting ceremony! Elsie's Place is a sandwhich shop with gaming.