NAACP sues xAI over air pollution near Memphis data center

NAACP sues xAI over air pollution near Memphis data center

Spread the love

The NAACP filed a lawsuit in federal court Tuesday against Elon Musk’s xAI, saying the company is illegally operating 27 methane gas turbines in Mississippi to power its Colossus 2 data center complex across the state line in Memphis.

In the lawsuit filed in the U.S. District Court for the Northern District of Mississippi, the NAACP says emissions from the gas turbines violate the Clean Air Act. The Colossus 2 data center near Memphis is the primary training facility for Grok-4, xAI’s next generation chatbot.

The NAACP says between August and December, xAI and its subsidiary MZX Tech, operated 27 gas turbines in Southaven, Miss., “without an air permit or regard for the health and safety of people living nearby.”

Represented by Earthjustice and the Southern Environmental Law Center, the NAACP is suing to halt xAI’s operations until the company obtains permits, installs the most effective pollution controls available, and pays financial penalties for every day that air quality violations occurred.

In response to the legal action, xAI confirmed commitment to environmental standards.

“The temporary power generation units are operating in compliance with all applicable laws,” a company statement said.

“A data center should not be a potential death sentence for a community’s health,” said Abre’ Conner, NAACP director of environmental and climate justice. “By looking to evade clean air laws to operate dirty turbines that emit pollution and known carcinogens, these companies are following a shameful, familiar pattern: asking Black and frontline communities to bear the toxic brunt of ‘innovation.’”

The Southern Environmental Law Center says xAI’s failure to obtain a permit for the power generation plant created health risks for families in northern Mississippi and Memphis in violation of the Clean Air Act, which requires major sources of pollution to obtain air permits before beginning construction or operations.

The plaintiffs contend the gas turbines emit pollutants like formaldehyde and nitrogen oxides into predominantly Black communities already overburdened by industrial pollution.

The NAACP says in the lawsuit that the gas turbines on the Colossus 2 site could potentially emit over 1,700 tons of nitrogen oxides annually, which would make it the largest industrial source of the pollutant in the 11-county Memphis metropolitan area.

The lawsuit filed Tuesday by the NAACP follows a legal fight in 2025 over xAI’s use of gas turbines without permits to power the Colossus 1 data center. In 2024, Mississippi and Tennessee officials allowed xAI to operate gas turbines without a permit because they were classified as “temporary” and “mobile” units intended to run for less than a year. Under this “temporary-mobile” exemption, no official tracking of toxic releases was required.

In June 2025, after the NAACP and the Southern Environmental Law Center issued a formal notice of intent to sue, xAI removed 20 turbines from the Colossus 1 site and eventually obtained permits for the remaining 15 units.

The Colossus 2 data center will host 555,000 Nvidia GPUs and that potentially require 2 gigawatts of generation capacity, according to xAI. At the Colossus 2 site, the company plans to train chatbots with improvements over previous versions that include advanced reasoning abilities, faster data processing, and near-instant response times for end users.

To help manage the massive power load, xAI reports it has deployed about 600 industrial-grade batteries with approximately 2.3 gigawatt-hours of storage designed to provide energy buffer at times of high energy usage by the Colossus data center while also capable of supplying the local grid during peak demand.

According to the NAACP, the gas turbines at the site still pose a significant risk, with potential annual emissions of 180 tons of fine particulate matter, 500 tons of carbon monoxide, and 19 tons of formaldehyde – a toxic, cancer-causing chemical.

“xAI’s continued operation of these turbines without a permit and without adequate pollution controls is not only illegal, it’s an insult to families living nearby who for months have expressed serious concerns about how air pollution from the company’s personal power plant could impact their health and well-being,” said Ben Grillot, senior attorney at the Southern Environmental Law Center, a party in the lawsuit.

Leave a Comment





Latest News Stories

Will County Board Graphic.01

Sunny Hill Nursing Home Implements Enhanced Infection Control and Safety Measures

Will County Public Health & Safety Committee Meeting | April 2, 2026 Article Summary: Sunny Hill Nursing Home has rolled out "enhanced barrier precautions" to prevent the spread of multi-drug...
Will County Finance Logo

Consultant Updates Finance Committee on Homer Glen Police Cost Study

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: A consultant hired to evaluate the financial implications of the Village of Homer Glen launching its own...
Beecher Softball ladycats

Beecher Varsity Softball Powers Past Sterling 12-1 Behind Johnson’s Two-Hitter

Sophomore Allie Johnson pitched a complete-game two-hitter, and the Beecher offense erupted for 11 hits to secure a commanding 12-1 non-conference victory over host Sterling in a five-inning matchup on...
Beecher Softball ladycats

Norkus Shines as Beecher Varsity Softball Blanks Harvard 9-0

Senior Taylor Norkus struck out 13 batters over six scoreless innings to lead the Beecher varsity softball team to a commanding 9-0 non-conference victory on the road against Harvard on...
Generic Track & Field Graphic

Dwight Sweeps Team Titles at St. Anne Invitational

The Dwight High School track and field program delivered a commanding all-around performance on Friday, April 10, sweeping both the boys' and girls' team titles at the 2026 St. Anne...
Beecher Baseball Bobcats

Massive Eight-Run Second Inning Propels Seneca Past Beecher

Seneca used a massive eight-run outburst in the bottom of the second inning to hold off Beecher 8-6 in a wild, defensively sloppy Friday non-conference matchup. Despite committing six errors...
—Photo courtesy of Laurie Lasseter

Fish fight: action-packed eagle pic wins March photo contest

Laurie Lasseter of Woodridge snapped a photo of an eagle and herring gull locked in battle recently, and the shot was picked as the March winner in the District's Preserve...
Police Crime

Illinois State Police Investigating Fatal Officer-Involved Shooting in Bradley

Article Summary: The Illinois State Police is investigating a fatal officer-involved shooting that occurred after Bradley Police officers encountered an armed man during a mid-day well-being check. Bradley Officer-Involved Shooting...
Monee Car Fire

Fire Department Responds to Monee Car Fire

Monee firefighters responded to a car fire on Manhattan-Monee Road April 10th. No injuries were reported.
NL Fire

New Lenox Firefighters Extinguish Garage Fire, Rescue Pets on Somerset Court

Article Summary: The New Lenox Fire Protection District quickly contained a Friday morning garage fire on Somerset Court, preventing the blaze from spreading to the home's main living area and...
WCO-Capital Improvements & IT Apr 07 214

Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county...
will county board meeting.6

Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities...
Will County Board Graphic.03

Will County Hires LEAP HR Consulting for $12,000 Strategic Plan

Will County Board Meeting | March 19, 2026 Article Summary: Seeking to unify its vision and improve onboarding for new members, the Will County Board will launch a four-month strategic...
Will County Finance Logo

Will County Finalizes 2025 Tax Levy at $159.5 Million, Limiting Rate Drops

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: The Will County Finance Committee reviewed the final 2025 tax levy extension numbers, which came in slightly...
Will County Board Graphic.02

Will County to Take Jurisdiction of Countyline Road Following $1.8 Million Agreement with Kankakee County

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: Will County will absorb a 4.27-mile stretch of Countyline Road into its highway system, aided by...