Will County P&Z Logo Planning Zoning

Will County Planning and Zoning Commission Recommends Denial of 6,099-Acre Earthrise Solar Project After Court-Ordered Hearing

Spread the love

Will County Board Special Planning and Zoning Commission Meeting | May 12, 2026

Article Summary: Following a court-mandated cross-examination hearing, the Will County Planning and Zoning Commission voted 1-4 to recommend denial of a special use permit for the massive Lincoln Solar Energy project spanning three townships.

Earthrise Solar Project Key Points:

  • The PZC voted 1-4 against the special use permit for the 600 MW solar facility (Ordinance #26-109 / Case ZC-25-129) proposed by Earthrise Energy.

  • The special meeting was mandated by a court order (26CH79) from Judge Breslin to allow plaintiffs to cross-examine developers due to alleged due process violations.

  • Plaintiffs argued the application was incomplete, citing missing field data for “farmed wetlands” and public safety risks.

  • The $1.2 billion project footprint encompasses roughly 6,099 acres across Manhattan, Green Garden, and Wilton townships.

The Will County Board Planning and Zoning Commission on Tuesday, May 12, 2026, voted 1-4 to recommend denial of a special use permit for a sprawling 6,099-acre commercial solar facility, following a contentious, court-ordered cross-examination hearing.

Earthrise Energy, operating under Lincoln Solar Energy, LLC, applied for a special use permit to build a 600-megawatt solar facility across 96 parcels in Manhattan, Green Garden, and Wilton townships. The facility would connect to the grid via the existing Lincoln natural gas peaking plant. While the PZC had previously voted to recommend denial in March, Tuesday’s special meeting was mandated by a temporary restraining order from Judge Breslin. The court order allowed plaintiffs to cross-examine the developers, a process the plaintiffs’ attorney claimed the county had illegally bypassed for years.

“The reason you haven’t heard this before is for some reason in this county there’s not been any cross-examination for years during a special use application,” Plaintiff Attorney Steven Becker told the commission. “That’s what we won in front of Judge Breslin… this is a new procedure that was apparently being bypassed by Will County unbeknownst to me.”

During the cross-examination, Becker grilled Earthrise Lead Developer Robert Kalbouss over the company’s environmental reviews, specifically focusing on the delineation of wetlands and the potential for heavy metal leaching into the groundwater. Becker argued that the application was incomplete because Earthrise relied primarily on a National Wetland Inventory (NWI) data set from the U.S. Fish and Wildlife Service rather than waiting for fields to lie fallow to properly field-delineate “farmed wetlands.”

“If a field is being tilled, you cannot determine hydrophytic vegetation. You have to wait until it is fallow,” Becker argued. “This application is woefully incomplete.”

Earthrise attorney Ben Jacobi fiercely defended the application, noting that the company updated its site plan on March 5, 2026, and submitted a supplemental memorandum on May 8 detailing complete field delineations. Jacobi stated that the project was designed to completely avoid all permanent impacts to wetlands.

“They’re going to avoid them all. They’re going to assume the jurisdiction of the wetland, and they’re going to avoid them all,” Jacobi said. “And so, that’s really important that that eliminates the wetland as an issue entirely.”

The developer also faced questions about why outreach meetings were not held in Green Garden or Wilton townships. Kalbouss confirmed that public information meetings were only hosted in Manhattan Township, citing “the hostility that we observed online from the township” as the reason for not holding open forums in the other jurisdictions.

Prior to the final vote on the special use permit, the PZC voted unanimously to amend conditions 3, 5, and 6 of the permit to match language recently approved by the Will County Board for the Plum Valley Solar project.

However, when the amended special use permit was called to a vote, it failed in a 1-4 split. Commissioner Lewis Navarat voted yes, while Vice Chairman John Kiefner, Commissioner Matt Garland, Commissioner Karen Warrick, and Chairman Hugh Stipan voted no.

The 192 variances associated with the project—allowing for 36-inch ground cover plant heights and a reduction in mandatory mowings—were previously approved during a March 31 meeting and were not subject to Tuesday’s vote. The PZC’s denial recommendation will now move forward to the Will County Board for final consideration.

Leave a Comment





Latest News Stories

Illinois GOP U.S. Senate candidates point to economy, Trump gains

Illinois GOP U.S. Senate candidates point to economy, Trump gains

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Economic issues are front and center for Republican U.S. Senate candidates in Illinois. Former Illinois GOP Chairman...
Meeting-Briefs

Meeting Summary and Briefs: Peotone Board of Education for August 18, 2025

The Peotone Board of Education’s August 18 meeting was defined by the district’s precarious financial situation. With a projected $4.2 million operating deficit and its borrowing capacity nearly exhausted, the...
Lawmaker criticizes $500 student board scholarships amid lowered K‑12 standards

Lawmaker criticizes $500 student board scholarships amid lowered K‑12 standards

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois student leaders serving on state higher education boards will now receive $500-per-semester scholarships under a...
Illinois news in brief: Work begins on $1.5 billion O'Hare expansion; Police catch man accused of road rage, shooting

Illinois news in brief: Work begins on $1.5 billion O’Hare expansion; Police catch man accused of road rage, shooting

By Jim Talamonti | The Center SquareThe Center Square Work begins on $1.5 billion O'Hare expansion A new round of construction has begun at O’Hare International Airport in Chicago. Airline...
Exec Cmte 8.14.25.4

Executive Committee Details Spending of $134 Million in Pandemic Relief Funds

Article Summary: Will County has expended 61% of its $134 million in federal American Rescue Plan Act (ARPA) funds, with significant investments made in infrastructure, health, and economic development. Officials...
Peotone-Committee-8.18.25.1

Facing Budget Crisis, Peotone Committee Questions Athletic Field Project

Committee of the Whole Article Summary: With Peotone School District 207-U on the verge of a financial crisis, board members are questioning the wisdom of moving forward with a long-awaited...
Meeting-Briefs

Committee Summary and Briefs: Peotone Board of Education Committee of the Whole

The Peotone School District 207-U is on a collision course with a major financial crisis, which dominated the Board of Education’s committee meeting on August 18. Facing a projected $4.2...
Soaring utility bills, solar federal tax credit cuts dominate Illinois energy debate

Soaring utility bills, solar federal tax credit cuts dominate Illinois energy debate

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Energy prices and clean energy policy took center stage during a senate energy and public utilities...

Illinois quick hits: Pritzker signs crypto regulations

By Jim Talamonti | The Center SquareThe Center Square Pritzker signs crypto regulations Gov. J.B. Pritzker has signed two laws to regulate cryptocurrency. Senate Bill 1797 requires cryptocurrency companies to...
Trucking industry leader: New law may drive business out of Illinois

Trucking industry leader: New law may drive business out of Illinois

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A trucking industry leader says more businesses may leave Illinois after the signing of Senate Bill 328....
Exec Cmte 8.14.25.3

Executive Committee Considers $12,000 Strategic Planning Initiative with University of St. Francis

Article Summary: The Will County Executive Committee is considering a proposal from the University of St. Francis to lead a six-month, $12,178 strategic planning process. The initiative is aimed at...
Exec Cmte 8.14.25.2

Executive Committee Members Decry Roadside Litter, Call for Action Against Garbage Haulers

Article Summary: Will County Executive Committee members expressed frustration over what they described as a worsening problem of litter blowing from garbage trucks across the county. Members called for better...
Ad Hoc.8.12.25.3

Will County Updates Solid Waste Ordinance, Increases Fines and Reporting to Landfill Committee

Article Summary: The Will County Ad-Hoc Ordinance Review Committee advanced an updated solid waste ordinance that doubles the maximum fine for violations and requires the county auditor's annual report to...
Ad Hoc.8.12.25.2

Citing Liability Concerns, Will County Committee Postpones Vote on Septic System Ordinance

Article Summary: The Will County Ad-Hoc Ordinance Review Committee postponed a vote on updating its sewer and sewage disposal ordinance after a member raised significant concerns about the county's liability...
Ad Hoc.8.12.25.1

Will County Moves to Repeal Obsolete 1972 Fire Hydrant Ordinance

Article Summary: An ordinance from 1972 regulating the placement and specifications of fire hydrants in Will County is set to be repealed after the Ad-Hoc Ordinance Review Committee approved its...