Beecher Community Unit School District 200-U Meeting | May 13, 2026

Article Summary: Beecher Community Unit School District 200-U board members on Wednesday, May 13, 2026, approved a $14,276 floor restoration contract with Citywide Facilities to strip and refinish more than two decades of wax buildup at Beecher Junior High School. They also approved removing the failing digital sign in front of the junior high, while the superintendent detailed a slate of additional summer projects across all three school buildings.

Summer Capital Projects Key Points:

  • $14,276 VCT floor restoration at Beecher Junior High awarded to Citywide Facilities; building expected to be closed for roughly three weeks in June.
  • Aging digital sign at Beecher Junior High to be removed entirely; board cited the existing vinyl signage as preferable.
  • Beecher High School old-gym floor to receive a $9,200 oil-based refinish from gym floor specialist Stalker, including replacement of 17 floorboards.
  • Elementary window replacement project and seal coating work at the junior high also moving forward this summer.

BEECHER — The Beecher Community Unit School District 200-U Board of Education on Wednesday, May 13, 2026, approved a $14,276 contract with Citywide Facilities to restore the floors at Beecher Junior High School, voted to remove the building’s aging digital sign, and heard a detailed summer construction outlook from Superintendent Dr. Jack Gaham.

The floor restoration contract was approved unanimously. Gaham told the board the project is necessary because the vinyl composition tile (VCT) floors at the junior high carry more than 20 years of wax buildup that has become impractical to maintain through routine waxing alone.

“We’re going to take the 20 years of wax and we’re going to … have Citywide strip those down back down to the original VCT, back to their origin instead of trying to replace these things,” Gaham said. “We can get it back down to the to the base level and we can start it fresh.”

The superintendent said Citywide Facilities will handle the stripping while the district’s own custodial staff will re-wax the floors and put the rooms back together. To prevent overlap between the contractor and district staff, Gaham said it is highly likely the junior high will be closed to district workers for roughly three weeks in June. “I’m going to give the company carte blanche to get it done,” he said.

Gaham added that he expects to bring an updated annual cleaning contract with Citywide back to the board at its next meeting, covering both the junior high and elementary buildings. “Both buildings have been very happy with this past year. So fingers crossed we can keep that,” he said.

Junior High Digital Sign Coming Down

In a separate unanimous vote, the board approved removing the digital sign at the front of Beecher Junior High School. The sign has been the subject of previous discussions about whether to repair, replace or remove it.

Dr. Kwasny initially indicated she was open to either path, but Gaham said a follow-up conversation produced a clearer recommendation. “At the end of the day her preference would be to to remove it altogether,” Gaham said, citing the existing vinyl signage already in place at the building as a strong visual identifier. Removal will be handled internally and is expected to cost less than $10,000.

Gym Floor, New Office, Other Work

Outside the formal action items, Gaham used his report to walk through the broader summer slate.

At Beecher High School, the long-running issue with the old gym floor has produced what Gaham called welcome news. After an evaluation by floor contractor Stalker, the school will not need to sand the floor down — a fix the superintendent said he had feared could climb into six figures. Instead, the company will replace 17 boards in the old gym, scrub the surface, and apply an oil-based finish, with the same treatment applied to the floor in the high school den. The total estimated cost is $9,200, Gaham said. The contractor told the district that a previous water-based finish was likely the cause of the heaving issues observed in the gym floor over the past year.

The high school will also gain a new office. An unused journalism lab will be converted into a dedicated office for a high school administrator who currently has to walk through another teacher’s classroom to reach his workspace, Gaham said. A new door will be installed as part of the conversion.

At Beecher Elementary School, district staff will scrub and wax the floors while a major window replacement project moves forward. At the junior high, parking lot seal coating previously approved by the board is also scheduled.

The board’s next regular meeting is set for Tuesday, June 10, 2026, at 6 p.m.

Leave a Comment





Latest News Stories

—photos by Jim Piacentini

Norkus Tosses Two-Hit Shutout, Beecher Offense Cruises Past Gardner-South Wilmington 10-0

Senior Taylor Norkus delivered a brilliant two-hit shutout to lead the Beecher varsity softball team to a 10-0 run-rule victory over conference rival Gardner-South Wilmington on Friday afternoon. Norkus was...
Washington Township Graphic.2

Washington Township Highway Department Weighs Quarter-Million Dollar Truck Purchase

Washington Township Board of Trustees Meeting | March 2, 2026 Article Summary: The Washington Township Road District is bracing for significant capital expenditures, with Highway Commissioner Mike Smith advising the...
Beecher Baseball Bobcats

Late Rally Propels Wilmington Past Beecher 7-5

The Wilmington varsity baseball team mounted a decisive four-run rally in the bottom of the sixth inning to erase a late deficit and secure a 7-5 home victory over non-conference...
Beecher Graphic.3

Beecher Looks to Broaden Scope of Water System Infrastructure Funds

Village of Beecher Meeting | April 13, 2026 Article Summary: The Village of Beecher is drafting an ordinance to amend its local code, allowing funds previously restricted strictly for "water...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board Ad-Hoc Ordinance Review Committee for April 14, 2026

Will County Board Ad-Hoc Ordinance Review Committee Meeting | April 14, 2026 The Will County Board Ad-Hoc Ordinance Review Committee held a highly efficient meeting on Tuesday, April 14, 2026,...
Will County Board Graphic.01

Executive Committee Advances Sweeping Updates to Adult Entertainment and Wireless Facilities Ordinances

Will County Board Executive Committee Meeting | April 9, 2026 Article Summary: The Will County Board Executive Committee advanced two major ordinances completely rewriting the county's regulations for Adult Entertainment...
Generic Track & Field Graphic

Bismarck-Henning-Rossville-Alvin Sweeps Team Titles at Watseka Coed Meet #3

The Bismarck-Henning-Rossville-Alvin (BHRA) track and field program put together a masterclass of depth and execution, sweeping both the boys' and girls' team championships at the Watseka Coed Meet #3 on...
Beecher Baseball Bobcats

Clifton Central Surges Past Beecher 14-9 Despite Van Ness’s Perfect Day at the Plate

The Beecher varsity baseball team suffered a tough 14-9 home conference loss on Thursday, falling to Clifton Central in a high-scoring, back-and-forth contest defined by massive momentum swings. Despite the...
Beecher Softball ladycats

Kvasnicka’s Perfect Day Sparks Beecher’s 10-0 Run-Rule Win Over Clifton Central

The Beecher varsity softball team utilized a massive second inning and a combined three-hit shutout to secure a 10-0, five-inning conference victory over visiting Clifton Central on Thursday afternoon. Beecher...
Beecher Softball ladycats

Norkus Tosses One-Hit Masterpiece, Beecher Offense Explodes in 14-0 Win

Senior Taylor Norkus delivered an absolutely dominant performance in the circle, striking out 15 batters to lead the Beecher varsity softball team to a 14-0 home conference victory over Clifton...
Will County Board Graphic.02

Ad-Hoc Committee: County Lowers Air Rifle Age to 13, Finds Airsoft Guns Beyond Local Regulatory Reach

Will County Board Ad-Hoc Ordinance Review Committee Meeting | April 14, 2026 Article Summary: The Will County Ad-Hoc Ordinance Review Committee advanced updates to its public peace ordinances, lowering the...
Will County Board Graphic.03

Executive Committee Approves Local Fire District Appointments, Faces Pushback Over Delayed Elwood Seat

Will County Board Executive Committee Meeting | April 9, 2026 Article Summary: The Will County Executive Committee approved a slate of appointments for several fire protection districts, including Manhattan and...
Beecher Fire Protection District graphic.1

Beecher Fire District Approves Emergency Structural Repairs for Station

Beecher Fire Protection District Meeting | February 26, 2026 Article Summary: The Beecher Fire Protection District Board of Trustees unanimously approved emergency structural repairs to the fire station during its...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for April 7, 2026

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 The Will County Board Finance Committee met on Tuesday, April 7, 2026, to review and finalize the county's 2025...
Will County Board Graphic.03

Ad-Hoc Committee: County’s Lack of Home Rule Stifles Effort to Ban Kratom and Non-Nicotine Vapes

Will County Board Ad-Hoc Ordinance Review Committee Meeting | April 14, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to its tobacco and alternative nicotine...