Beecher Village Board Meeting | May 11, 2026

Article Summary: The Beecher Village Board on Monday, May 11, 2026, unanimously approved a $36,000 contract with Asterra to provide satellite-based leak detection services, a new technology the village hopes will identify subsurface water main leaks before they surface and drive up pumping costs.

Asterra Leak Detection Key Points:

  • The board accepted a $36,000 proposal from Asterra for satellite leak detection, well below the $72,000 to $108,000 range trustees had been bracing for.
  • Service includes a five-person crew working on-site for a week to narrow satellite findings to within an 18-foot radius.
  • Public works officials hope the system will identify “catastrophic” subsurface losses currently driving up pump-to-bill ratios.
  • The board indicated the service could become a biennial rather than annual expense if results are strong.

BEECHER — The Beecher Village Board on Monday, May 11, 2026, unanimously approved a $36,000 contract with Asterra to provide satellite-based leak detection services, a tool village officials hope will dramatically reduce unaccounted-for water loss by pinpointing leaks below ground that don’t surface in visible breaks.

Trustee Erik Gardner, who chairs the Public Works Committee, introduced the motion after telling colleagues that the price came in well under expectations. “It’s uh very promising and it was we were kind of figuring that was it could be maybe two to three times more expensive than this,” Gardner said. “So it was it was pretty surprising but um pretty promising.”

The technology differs from traditional surface-leak surveys. According to the public works superintendent, who briefed the board, the Asterra satellite scan is calibrated to detect chlorinated municipal water specifically, distinguishing treated drinking water from naturally occurring sources such as rivers, streams or saltwater. The result is a system tuned to find leaks from the village’s distribution mains rather than chase false positives from surface water.

How the Service Works

Once satellite data is analyzed, Asterra deploys a five-person crew to Beecher for roughly a week. That crew uses the satellite findings to narrow each suspected leak to within an 18-foot radius, the superintendent told the board, giving village staff a tight target area for follow-up excavation. “They’ll have a fiveman crew on site as well for a week and trying to pinpoint within an 18t radius of what the satellite’s telling them,” he said. “So, kind of get us at least in a general direction of where some of the bigger leaks are below grade.”

The superintendent acknowledged the technology is unproven for Beecher’s distribution system. “It’s uh pretty sounded pretty promising,” he said. “Um it’s definitely a a new technology era that we’re, you know, trying to give it a shot.”

The Financial Case

Trustees framed the $36,000 expense as a likely cost-saver based on the village’s current pump-to-bill ratio — the gap between water pumped from village wells and water actually billed to customers. That gap represents loss, much of it presumed to be from undetected underground leaks.

“If we find something major which I’m hoping that we do,” the superintendent said, “with our pump to build ratios we’re we’re hoping to find something you know catastrophic that we’re losing all this water um so it’ll pay for itself if we do just by the cost of what you know what we’re pumping versus what we’re billing.”

Trustees also pointed to avoided wear on water-system equipment. Gardner noted the village paid roughly $60,000 last year to replace a pump at Well 5 — a cost that mounts when undetected leaks force pumps to run harder and longer than necessary. Reducing pumping volume also cuts chemical treatment costs, another trustee added during discussion.

If results justify the expense, officials indicated the service may not need to be repeated annually. “Maybe every other year we talked about just to make sure,” the superintendent said.

The motion to accept the Asterra proposal passed by a unanimous roll-call vote of trustees Gardner, Roger Stacey, Brian Diachenko, Todd Kraus, Jessica Smith and Joe Tieri.

The Asterra contract was the second public works proposal approved during the meeting. The board also accepted a proposal from Baxter & Woodman for National Pollutant Discharge Elimination System Municipal Separate Storm Sewer System (MS4) program assistance for 2026 in an amount not to exceed $13,900. Gardner noted village staff may be able to reduce the final cost on the stormwater contract by handling portions of the work in-house.

Leave a Comment





Latest News Stories

AARP_Fraud

AARP Urges Will County to Ban Cryptocurrency Kiosks Amid Exploding Senior Fraud Rates

Will County Board Legislative Committee Meeting | April 7, 2026 Article Summary: Representatives from AARP Illinois presented alarming new FBI data to the Will County Board Legislative Committee, revealing $11...
Will County Board Graphic.03

Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3...
Will County Board Graphic.01

Sunny Hill Nursing Home Implements Enhanced Infection Control and Safety Measures

Will County Public Health & Safety Committee Meeting | April 2, 2026 Article Summary: Sunny Hill Nursing Home has rolled out "enhanced barrier precautions" to prevent the spread of multi-drug...
Will County Finance Logo

Consultant Updates Finance Committee on Homer Glen Police Cost Study

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: A consultant hired to evaluate the financial implications of the Village of Homer Glen launching its own...
Beecher Softball ladycats

Beecher Varsity Softball Powers Past Sterling 12-1 Behind Johnson’s Two-Hitter

Sophomore Allie Johnson pitched a complete-game two-hitter, and the Beecher offense erupted for 11 hits to secure a commanding 12-1 non-conference victory over host Sterling in a five-inning matchup on...
Beecher Softball ladycats

Norkus Shines as Beecher Varsity Softball Blanks Harvard 9-0

Senior Taylor Norkus struck out 13 batters over six scoreless innings to lead the Beecher varsity softball team to a commanding 9-0 non-conference victory on the road against Harvard on...
Generic Track & Field Graphic

Dwight Sweeps Team Titles at St. Anne Invitational

The Dwight High School track and field program delivered a commanding all-around performance on Friday, April 10, sweeping both the boys' and girls' team titles at the 2026 St. Anne...
Beecher Baseball Bobcats

Massive Eight-Run Second Inning Propels Seneca Past Beecher

Seneca used a massive eight-run outburst in the bottom of the second inning to hold off Beecher 8-6 in a wild, defensively sloppy Friday non-conference matchup. Despite committing six errors...
—Photo courtesy of Laurie Lasseter

Fish fight: action-packed eagle pic wins March photo contest

Laurie Lasseter of Woodridge snapped a photo of an eagle and herring gull locked in battle recently, and the shot was picked as the March winner in the District's Preserve...
Police Crime

Illinois State Police Investigating Fatal Officer-Involved Shooting in Bradley

Article Summary: The Illinois State Police is investigating a fatal officer-involved shooting that occurred after Bradley Police officers encountered an armed man during a mid-day well-being check. Bradley Officer-Involved Shooting...
Monee Car Fire

Fire Department Responds to Monee Car Fire

Monee firefighters responded to a car fire on Manhattan-Monee Road April 10th. No injuries were reported.
NL Fire

New Lenox Firefighters Extinguish Garage Fire, Rescue Pets on Somerset Court

Article Summary: The New Lenox Fire Protection District quickly contained a Friday morning garage fire on Somerset Court, preventing the blaze from spreading to the home's main living area and...
WCO-Capital Improvements & IT Apr 07 214

Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county...
will county board meeting.6

Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities...
Will County Board Graphic.03

Will County Hires LEAP HR Consulting for $12,000 Strategic Plan

Will County Board Meeting | March 19, 2026 Article Summary: Seeking to unify its vision and improve onboarding for new members, the Will County Board will launch a four-month strategic...