Watchdog: Canceled NASA contracts more than doubled in cost
A new federal watchdog report found contract values on canceled Artemis systems more than doubled, to $5.9 billion, and NASA still hasn’t disclosed what its Moon-to-Mars program will cost.
NASA Administrator Jared Isaacman and Moon Base program manager Carlos García-Galán will hold a virtual briefing at 2:30 p.m. EDT June 30 to discuss the next round of lunar lander mission awards and preview upcoming contracting opportunities.
The briefing comes as the NASA Office of Inspector General reported Wednesday that four Artemis systems NASA canceled or repurposed earlier this year saw their combined contract values grow from $2.8 billion to $5.9 billion. The watchdog projected costs would have climbed even higher had work continued.
NASA has not provided a total cost estimate for its Moon-to-Mars program. At a March briefing, Administrator Jared Isaacman said NASA would invest approximately $20 billion over seven years to build the moon base, but did not provide a total cost for the broader program when reporters asked about funding.
The watchdog projected the Boeing-built Exploration Upper Stage alone would have cost $3.7 billion if completed, nearly four times its original $962 million contract value and about 7.5 years behind schedule.
NASA’s acting inspector general testified before Congress in January 2024 that the Artemis program alone was projected to exceed $93 billion through 2025. The inspector general also projected the SLS/Orion system would cost at least $4.2 billion per launch for the program’s first four missions, not including $42 billion in formulation and development costs.
The Government Accountability Office has designated NASA acquisition management a high-risk area for more than 30 years.
The agency faces budget uncertainty. The White House proposed cutting NASA from $24.4 billion to $18.8 billion, a 23% reduction, while the House has advanced legislation keeping funding flat.
U.S. Rep. Brian Babin, R-Texas, chairman of the House Science, Space and Technology Committee, said the White House proposal could not support President Donald Trump’s own exploration goals.
A NASA spokesperson said the agency was unlikely to meet a request for comment before publication on the total cost of its Moon-to-Mars program or when such an estimate would be available.
NASA officials said in March that canceled Gateway hardware would be repurposed for the Moon Base, but the inspector general reported Wednesday that NASA has yet to decide whether or how to use it.
Latest News Stories
Pritzker: State will not build stadium for Bears
California doctor indicted in Louisiana for sending abortion pills
Bill Clinton skips out on closed-door deposition
Illinois uses state-run ACA exchange to extend deadline
Trump says inflation data shows Fed can cut interest rates
Allstate homeowners rate hike sparks debate over Illinois insurance oversight
Trump tells Iranian protesters help is on the way, encourages uprising
Sen. Kelly sues Hegseth over effort to reduce retirement pay
Illinois interstate shootings decline
WATCH: State sues Trump admin over enforcement tactics; No tax on tips proposal filed
Will the Clintons testify on Epstein relationship this week?
Dems move to almost entirely block fed immigration enforcement in IL