Watchdog: Canceled NASA contracts more than doubled in cost

Watchdog: Canceled NASA contracts more than doubled in cost

Spread the love

A new federal watchdog report found contract values on canceled Artemis systems more than doubled, to $5.9 billion, and NASA still hasn’t disclosed what its Moon-to-Mars program will cost.

NASA Administrator Jared Isaacman and Moon Base program manager Carlos García-Galán will hold a virtual briefing at 2:30 p.m. EDT June 30 to discuss the next round of lunar lander mission awards and preview upcoming contracting opportunities.

The briefing comes as the NASA Office of Inspector General reported Wednesday that four Artemis systems NASA canceled or repurposed earlier this year saw their combined contract values grow from $2.8 billion to $5.9 billion. The watchdog projected costs would have climbed even higher had work continued.

NASA has not provided a total cost estimate for its Moon-to-Mars program. At a March briefing, Administrator Jared Isaacman said NASA would invest approximately $20 billion over seven years to build the moon base, but did not provide a total cost for the broader program when reporters asked about funding.

The watchdog projected the Boeing-built Exploration Upper Stage alone would have cost $3.7 billion if completed, nearly four times its original $962 million contract value and about 7.5 years behind schedule.

NASA’s acting inspector general testified before Congress in January 2024 that the Artemis program alone was projected to exceed $93 billion through 2025. The inspector general also projected the SLS/Orion system would cost at least $4.2 billion per launch for the program’s first four missions, not including $42 billion in formulation and development costs.

The Government Accountability Office has designated NASA acquisition management a high-risk area for more than 30 years.

The agency faces budget uncertainty. The White House proposed cutting NASA from $24.4 billion to $18.8 billion, a 23% reduction, while the House has advanced legislation keeping funding flat.

U.S. Rep. Brian Babin, R-Texas, chairman of the House Science, Space and Technology Committee, said the White House proposal could not support President Donald Trump’s own exploration goals.

A NASA spokesperson said the agency was unlikely to meet a request for comment before publication on the total cost of its Moon-to-Mars program or when such an estimate would be available.

NASA officials said in March that canceled Gateway hardware would be repurposed for the Moon Base, but the inspector general reported Wednesday that NASA has yet to decide whether or how to use it.

Leave a Comment





Latest News Stories

Beecher Graphic.1

Beecher Overhauls Village Governance, Dissolves Key Commissions in Code Update

Article Summary: The Village of Beecher has fundamentally restructured its governmental framework, approving a pair of ordinances that redefine the roles of trustees, resize the Police Commission, and formally dissolve...
Beecher Graphic.3

Beecher to Explore New Banking Relationship, Considers Annual Bids for Services

Article Summary: The Village of Beecher is poised to change where it banks and how it manages its financial partnerships, following a discussion at the July 14 board meeting. After...
Beecher Graphic.4

Beecher Nuisance Property Owner Makes ‘Substantial Effort’ to Clean Up

Article Summary: The owner of a long-problematic property on Catalpa Street has cleaned up the yard and ordered a dumpster, showing significant progress after years of complaints and recent threats...

Meeting Summary and Briefs: Village of Beecher Board of Trustees for July 14, 2025

The Beecher Village Board passed a major overhaul of its governmental structure at its meeting on July 14, approving ordinances that dissolve the Planning and Zoning and Beautification Commissions and...
WCO Exec Cmte July 10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO Exec Cmte July 10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
Screenshot 2025-08-22 at 8.12.43 PM

Beecher School Board Begins Overhaul of District Goals, Focusing on Transparency, Inclusivity, and Student Success

Article Summary: The Beecher Board of Education has initiated a comprehensive update of its district-wide goals, beginning a process to replace a strategic plan that has been in place since...
beecher ilinois school board graphic.12

Beecher School Board Finalizes Policy Updates, Approves New Student Handbook

Article Summary: The Beecher Board of Education gave its final approval to a series of policy updates and a revised Student Handbook for the 2025-2026 school year. The unanimous votes...
beecher ilinois school board graphic.5

District Modifies Janitorial Contract, Saving Money by Bringing Junior High In-House

Article Summary: The Beecher Board of Education approved a new janitorial contract with Citywide Janitorial for the 2025-2026 fiscal year that covers only the elementary school, a change that will...
Meeting Briefs

Meeting Summary and Briefs: Beecher Board of Education for July 9, 2025

The Beecher Board of Education began the process of creating a new five-year strategic plan by holding an in-depth discussion to overhaul its district goals at its July 9 meeting....
washington township graphic.1

Washington Township to Reduce Office Hours in Summer Trial

Article Summary: The Washington Township Board of Trustees has approved a plan to reduce public office hours for a trial period this summer, citing less foot traffic and potential cost...
washington township graphic.2

Washington Township Opts for $1,050 AC Repair Over $10,200 Replacement

Article Summary: The Washington Township Board of Trustees chose to repair two non-functional, 25-year-old air conditioning units for $1,050 rather than pursue a full replacement of all three units at...
washington township graphic.3

Property Assessments Set to Rise Across Washington Township

Article Summary: Washington Township Assessor Pat Peters has advised residents that property assessments are expected to rise for nearly every property in the township. The increase is due to a...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for July 7, 2025

The Washington Township Board of Trustees voted to reduce its public office hours for the summer, a key decision made during its meeting on Monday, July 7. Citing a decline...