Beecher 200-U Board of Education Meeting | June 10, 2026

Article Summary: Beecher 200-U administrators told the board that roofing, window and floor projects are progressing across the elementary, junior high and high school buildings, with the elementary’s new second-floor windows expected to be finished by early July. The board declined to act on an $11,000 add-on parapet quote, directing staff to seek competing bids first.

Summer Construction Key Points:

  • New roofing and second-floor windows at Beecher Elementary are expected to wrap by late June or early July; floor restoration is underway at the junior high.
  • Work is being drawn from the district’s Health Life Safety fund, reported in the treasurer’s update at roughly $478,000.
  • The board held off on an $11,000 change order to cap a lower parapet section, asking staff to gather additional quotes.
  • Rain delayed the elementary roof start by two days, but crews were back on the roof the day of the meeting.

The update came during the superintendent’s report at the board’s regular meeting, held at 6 p.m. in the Beecher High School library. Superintendent Jack Gaham walked the board through projects that began almost immediately after the school year ended, framing them as Health Life Safety improvements — the category Illinois districts use for code, roofing and building-safety work.

Projects Across Three Buildings

At Beecher Elementary, a roofing contractor the district referred to as Langles had started the roofing and parapet work and was on site the day of the meeting, Gaham said. The crew got going two days late because of rain, but he estimated the roofing would take about two weeks, with new second-floor windows on roughly the same timeline.

“You should have a whole new second floor by the end of June, hopefully no later than early July,” Gaham told the board. He said the new windows would resemble the building’s lower-level units — a metal top section beneath the drop ceiling, the window itself, and sections that open. Gaham and Maintenance Director Nathan Stanula met with the roofing crew on the roof the prior Wednesday to review the scope.

At the junior high, crews had already completed door work and begun stripping floors down to the underlying tile ahead of re-waxing, which Gaham said Stanula expected to start on the athletic hallway the following week. “It’s unbelievable how many layers of wax,” the superintendent said, noting the floors had not been taken down to bare tile in roughly two decades. At the elementary, a closet door flagged by the fire marshal as an impermissible residential-style door was also upgraded, and two classrooms received new doors that did not require the heavier framing work needed elsewhere.

Board Holds Off on $11,000 Parapet Quote

Gaham also raised a possible add-on: while meeting with the project’s construction manager — referred to in the meeting as GRP — on the elementary roof, a representative named Jeremy offered to have the roofing company quote capping work on a lower parapet section. The figure came back at $11,000.

Gaham told the board he could not vouch for the number on its own. “I can’t tell you if this is a good number or a bad number,” he said, adding that Stanula was not especially concerned about the condition and that the work could be handled later by another vendor. Because the item would be a change order rather than a new contract, no vote was required; the board could simply authorize it. Members instead signaled they wanted competing quotes before committing, and Gaham said he would tell the contractor to proceed with the existing scope and revisit the parapet later.

The exact contract values for the larger roofing, window and flooring work were not read into the record at the meeting, and the treasurer’s report — which included the Health Life Safety fund balance — was delivered with several figures that were difficult to capture from the meeting audio. Gaham noted the Health Life Safety balance “will start going down with the project starting.”


Leave a Comment





Latest News Stories

Illinois quick hits: DHS ordered to address ICE facility conditions; Garcia explains retirement decision

Illinois quick hits: DHS ordered to address ICE facility conditions; Garcia explains retirement decision

By Jim Talamonti | The Center SquareThe Center Square DHS ordered to address ICE facility conditions A U.S. District Court judge in Chicago has issued a temporary restraining order directing...
Congressional Perks: Luxury cars and mileage result in big costs for taxpayers

Congressional Perks: Luxury cars and mileage result in big costs for taxpayers

By Arthur Kane | The Center SquareThe Center Square (The Center Square) – U.S. Reps Darrell Issa, R-Calif., and David Scott, D-Ga., have each had taxpayers pay as much as...
Illinois quick hits: $20 million for Alton housing project; alleged migrant assaults reported

Illinois quick hits: $20 million for Alton housing project; alleged migrant assaults reported

By Jim Talamonti | The Center SquareThe Center Square $20 million for Alton housing project Gov. J.B. Pritzker and the Illinois Housing Development Authority announced the opening of a $20...

WATCH: Illinois DCFS can’t locate documents showing number of missing children

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Documents to show the number of missing youth in care from the Department of Children and Family...
Will Dial-A-Ride Service

Will County Committee Advances Phased Takeover of Central Will Dial-A-Ride Service

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved a five-year plan to consolidate the Central Will Dial-A-Ride service into its...
Meeting Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for September 25, 2025

Beecher Fire Protection District Board of Trustees Meeting | September 25, 2025 The Beecher Fire Protection District Board of Trustees approved a major capital expense at its meeting on Thursday,...
Meeting-Briefs

Meeting Summary and Briefs: Village of Beecher for October 27, 2025

Village of Beecher Board Meeting | October 27, 2025 The Beecher Village Board weighed in on two major solar farm proposals during its meeting on Monday, October 27, 2025. The...
Beecher Fire Protection District graphic.1

Beecher Fire District Approves Over $27,000 for New LED Station Sign

Beecher Fire Protection District Board of Trustees Meeting | September 25, 2025 Article Summary: The Beecher Fire Protection District Board of Trustees has awarded a contract worth more than $27,000 to...
Brush Pickup

Final Brush Collection of the Season

The Beecher Public Works department has announced it will conduct one final pass for residential brush collection on Tuesday, November 4. This will be the last opportunity for residents to have...
Beecher Graphic.3

Beecher Hires New Firm for Financial Oversight, Reaffirms Banking Relationship

Village of Beecher Board Meeting | October 27, 2025 Article Summary: The Beecher Village Board took two key financial actions, approving an agreement with Pasbrig & Associates, LLC for accounting...
Beecher Police Graphic

Beecher Police Department to Get New In-Car Cameras for $60,255

Village of Beecher Board Meeting | October 27, 2025 Article Summary: The Beecher Village Board has approved the purchase of a new in-car camera system for the police department from...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Public Library District for September 16, 2025

Beecher Public Library District Meeting | September 16, 2025 The Beecher Public Library District board saw a significant leadership change at its Tuesday, September 16, 2025, meeting, electing Douglas Short...
solar panels photovoltaics in solar farm

Beecher Board Declines to Support Indiana Avenue Solar Project

Village of Beecher Board Meeting | October 27, 2025 Article Summary: The Beecher Village Board effectively withheld its support for a proposed community solar farm on Indiana Avenue, as a...
solar panels photovoltaics in solar farm

Beecher Board Backs Major Solar Project, Securing $100,000 for Village

Village of Beecher Board Meeting | October 27, 2025 Article Summary: The Village of Beecher has agreed to support Earthrise Energy's large-scale Plum Valley Solar project after negotiating a Community...
beecher illinois public library graphic.3

Digital Checkouts and Summer Programs See High Engagement at Beecher Library

Beecher Public Library District Meeting | September 16, 2025 Article Summary: The Beecher Public Library reported a successful summer with high community engagement, including record usage of its digital media platforms...