Beecher District Pushes Summer Roof, Window Projects Toward Fall Deadline

Spread the love

Beecher 200-U Board of Education Meeting | June 10, 2026

Article Summary: Beecher 200-U administrators told the board that roofing, window and floor projects are progressing across the elementary, junior high and high school buildings, with the elementary’s new second-floor windows expected to be finished by early July. The board declined to act on an $11,000 add-on parapet quote, directing staff to seek competing bids first.

Summer Construction Key Points:

  • New roofing and second-floor windows at Beecher Elementary are expected to wrap by late June or early July; floor restoration is underway at the junior high.
  • Work is being drawn from the district’s Health Life Safety fund, reported in the treasurer’s update at roughly $478,000.
  • The board held off on an $11,000 change order to cap a lower parapet section, asking staff to gather additional quotes.
  • Rain delayed the elementary roof start by two days, but crews were back on the roof the day of the meeting.

The update came during the superintendent’s report at the board’s regular meeting, held at 6 p.m. in the Beecher High School library. Superintendent Jack Gaham walked the board through projects that began almost immediately after the school year ended, framing them as Health Life Safety improvements — the category Illinois districts use for code, roofing and building-safety work.

Projects Across Three Buildings

At Beecher Elementary, a roofing contractor the district referred to as Langles had started the roofing and parapet work and was on site the day of the meeting, Gaham said. The crew got going two days late because of rain, but he estimated the roofing would take about two weeks, with new second-floor windows on roughly the same timeline.

“You should have a whole new second floor by the end of June, hopefully no later than early July,” Gaham told the board. He said the new windows would resemble the building’s lower-level units — a metal top section beneath the drop ceiling, the window itself, and sections that open. Gaham and Maintenance Director Nathan Stanula met with the roofing crew on the roof the prior Wednesday to review the scope.

At the junior high, crews had already completed door work and begun stripping floors down to the underlying tile ahead of re-waxing, which Gaham said Stanula expected to start on the athletic hallway the following week. “It’s unbelievable how many layers of wax,” the superintendent said, noting the floors had not been taken down to bare tile in roughly two decades. At the elementary, a closet door flagged by the fire marshal as an impermissible residential-style door was also upgraded, and two classrooms received new doors that did not require the heavier framing work needed elsewhere.

Board Holds Off on $11,000 Parapet Quote

Gaham also raised a possible add-on: while meeting with the project’s construction manager — referred to in the meeting as GRP — on the elementary roof, a representative named Jeremy offered to have the roofing company quote capping work on a lower parapet section. The figure came back at $11,000.

Gaham told the board he could not vouch for the number on its own. “I can’t tell you if this is a good number or a bad number,” he said, adding that Stanula was not especially concerned about the condition and that the work could be handled later by another vendor. Because the item would be a change order rather than a new contract, no vote was required; the board could simply authorize it. Members instead signaled they wanted competing quotes before committing, and Gaham said he would tell the contractor to proceed with the existing scope and revisit the parapet later.

The exact contract values for the larger roofing, window and flooring work were not read into the record at the meeting, and the treasurer’s report — which included the Health Life Safety fund balance — was delivered with several figures that were difficult to capture from the meeting audio. Gaham noted the Health Life Safety balance “will start going down with the project starting.”


Leave a Comment





Latest News Stories

Beecher Fire Protection District graphic.3

Beecher Fire District Bolsters Staff with Four New Part-Time Hires

Article Summary: The Beecher Fire Protection District has added four new part-time emergency responders to its roster, a move that enhances its operational readiness and ability to serve the community....
Beecher Fire Protection District graphic.1

Beecher Fire District Reorganizes Board, Approves New Record System and Community Donations

Article Summary: The Beecher Fire Protection District Board of Trustees has established its leadership for the upcoming year, reappointing Margie Cook as president, while also approving a major technology upgrade...
JJC Graphic Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Joliet Junior college. Graphic Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Joliet Junior college. Graphic Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet Junior college. Graphic Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Joliet Junior college. Graphic Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...
Meeting Briefs

Meeting Summary: Joliet Junior College Board of Trustees for June 25, 2025

The Joliet Junior College Board of Trustees met on Wednesday, June 25, 2025. Key actions included the approval of the fiscal year 2026 budget after a contentious debate and hearing...
Beecher Graphic.4

Beecher Faces $202,000 Revenue Loss, Considers Local 1% Grocery Tax

Article Summary: The Village of Beecher is contemplating the implementation of a local 1% grocery tax to prevent a significant budget shortfall of over $202,000 annually. This move comes in...
Beecher Graphic.1

Beecher Amends Zoning Ordinance to Add Regulations for Solar and Wind Energy

Article Summary: The Beecher Village Board has approved text amendments to its zoning ordinance to formally incorporate regulations for solar and wind energy systems, which had previously been omitted. The...
Beecher Graphic.3

Beecher Police Records Clerk Linda Krug to Retire After 27 Years

Article Summary: Linda Krug, a Police Department Records Clerk for the Village of Beecher, is retiring after 27 years of dedicated service. Police Chief Terry Lemming praised Krug as a...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for June 23, 2025

The Beecher Village Board used its June 23 meeting to address major upcoming fiscal and policy changes, including a state-level decision that could cost the village over $200,000 in annual...
Will County Board Meeting June 18, 2025

Will County Board Halts Transportation Plan After Contentious 143rd Street Debate

The Will County Board voted Wednesday to send its five-year, multi-million dollar transportation improvement plan back to committee, effectively pausing all projects after a lengthy and heated debate over the...
Will County Board Meeting June 18, 2025

Will County Board Upholds Zoning Denials, Rejecting Developer Appeals

The Will County Board on Wednesday backed its Planning and Zoning Commission (PZC), denying two separate appeals from property owners who sought to overturn the commission’s recommendations against their projects....
Will County Board Meeting June 18, 2025

Split Vote Halts Monee Truck Terminal Project

A proposed truck terminal on vacant land at West Monee-Manhattan Road in Monee Township was stopped in its tracks Wednesday after the Will County Board delivered a split decision on...