Beecher District Pushes Summer Roof, Window Projects Toward Fall Deadline

Spread the love

Beecher 200-U Board of Education Meeting | June 10, 2026

Article Summary: Beecher 200-U administrators told the board that roofing, window and floor projects are progressing across the elementary, junior high and high school buildings, with the elementary’s new second-floor windows expected to be finished by early July. The board declined to act on an $11,000 add-on parapet quote, directing staff to seek competing bids first.

Summer Construction Key Points:

  • New roofing and second-floor windows at Beecher Elementary are expected to wrap by late June or early July; floor restoration is underway at the junior high.
  • Work is being drawn from the district’s Health Life Safety fund, reported in the treasurer’s update at roughly $478,000.
  • The board held off on an $11,000 change order to cap a lower parapet section, asking staff to gather additional quotes.
  • Rain delayed the elementary roof start by two days, but crews were back on the roof the day of the meeting.

The update came during the superintendent’s report at the board’s regular meeting, held at 6 p.m. in the Beecher High School library. Superintendent Jack Gaham walked the board through projects that began almost immediately after the school year ended, framing them as Health Life Safety improvements — the category Illinois districts use for code, roofing and building-safety work.

Projects Across Three Buildings

At Beecher Elementary, a roofing contractor the district referred to as Langles had started the roofing and parapet work and was on site the day of the meeting, Gaham said. The crew got going two days late because of rain, but he estimated the roofing would take about two weeks, with new second-floor windows on roughly the same timeline.

“You should have a whole new second floor by the end of June, hopefully no later than early July,” Gaham told the board. He said the new windows would resemble the building’s lower-level units — a metal top section beneath the drop ceiling, the window itself, and sections that open. Gaham and Maintenance Director Nathan Stanula met with the roofing crew on the roof the prior Wednesday to review the scope.

At the junior high, crews had already completed door work and begun stripping floors down to the underlying tile ahead of re-waxing, which Gaham said Stanula expected to start on the athletic hallway the following week. “It’s unbelievable how many layers of wax,” the superintendent said, noting the floors had not been taken down to bare tile in roughly two decades. At the elementary, a closet door flagged by the fire marshal as an impermissible residential-style door was also upgraded, and two classrooms received new doors that did not require the heavier framing work needed elsewhere.

Board Holds Off on $11,000 Parapet Quote

Gaham also raised a possible add-on: while meeting with the project’s construction manager — referred to in the meeting as GRP — on the elementary roof, a representative named Jeremy offered to have the roofing company quote capping work on a lower parapet section. The figure came back at $11,000.

Gaham told the board he could not vouch for the number on its own. “I can’t tell you if this is a good number or a bad number,” he said, adding that Stanula was not especially concerned about the condition and that the work could be handled later by another vendor. Because the item would be a change order rather than a new contract, no vote was required; the board could simply authorize it. Members instead signaled they wanted competing quotes before committing, and Gaham said he would tell the contractor to proceed with the existing scope and revisit the parapet later.

The exact contract values for the larger roofing, window and flooring work were not read into the record at the meeting, and the treasurer’s report — which included the Health Life Safety fund balance — was delivered with several figures that were difficult to capture from the meeting audio. Gaham noted the Health Life Safety balance “will start going down with the project starting.”


Leave a Comment





Latest News Stories

Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
will county Committee-Legislative.Graphic

State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks

Legislative Committee Meeting | March 2026 Article Summary: During a state legislative update, Will County Board members expressed deep concerns over Governor J.B. Pritzker's continued push to mandate Accessory Dwelling Units...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...
Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
Beecher Graphic.1

Beecher Village Board Approves Street Sweeping Contract and State Right-of-Way Resolution

Village of Beecher Board of Trustees Meeting | March 9, 2026 Article Summary: The Beecher Village Board approved a $6,200 contract for comprehensive commercial street sweeping to maintain environmental compliance,...
Beecher Elementary school Graphic

Beecher Elementary Principal Resigns Amid Slew of Personnel and Contract Approvals

Beecher Board of Education Meeting | March 11, 2026 Article SummaryBeecher School District 200U approved a slate of personnel changes, most notably accepting the resignation of Elementary School Principal Nicole...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...
Will County Board Graphic.04

Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Public Works and Transportation Committee authorized a slate of professional services and construction agreements Tuesday to...
Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to...
will county Committee-Legislative.Graphic

Will County Board Backs $10 Million State Public Health Grant Increase Amid Funding Cuts

Legislative Committee Meeting | March 2026 Article Summary: The Will County Legislative Committee unanimously approved a resolution supporting a state legislative push to increase the Local Health Protection Grant by $10...