Central Ohio data center will have its own power plant
An Ohio state board has approved a natural gas-powered electric generation plant in Licking County to serve a data center, saying taxpayers and ratepayers won’t pay for power at the center.
The power will be consumed by Sidecat, LLC, an affiliate of Meta Platforms, Inc., according to a news release by the Ohio Power Siting Board, which approved the construction of the 250-megawatt natural gas plant.
“Taxpayers and ratepayers will not pay any of the costs,” board spokesman Matthew Butler told The Center Square.
The gas plant, which will be built on 109 acres, will not be physically connected to the electric power grid but will serve only the data center, the release said.
“The project will incorporate 116 MW of battery energy storage to accommodate fluctuations in demand and mitigate unplanned outages,” according to the news release.
The plant will be constructed and operated by Will-Power PH, LLC, the siting board said.
“Will-Power OH must adhere to 36 conditions designed to minimize potential impacts during construction and operation.,” the news release said.
The project will be “within the city of New Albany’s Technology Manufacturing District (TMD) Zone which is a regionally significant corridor for economic growth and development,” according to state documents.
Will-Power will be responsible for the power generation facility design, site development, earthwork, construction, restoration, and operation of the facility.
Will-Power will “own the power generation property, equipment, structures, and on-site Improvements,” according to state documents.
This is the latest in a string of data centers announced for Ohio. The state already has 224 data centers, according to Data Center Maps, which tracks the industry.
Latest News Stories
Beecher High School Slated for Over $88,000 in Major Plumbing Repairs
Beecher School Board Issues Suspension, Formal Notice to Remedy to Employee
Dr. Marie Hansel Appointed to Fill Vacancy on Beecher School Board
Beecher School Board Approves Amended Budget, New Staff Hires
Meeting Summary and Briefs: Beecher Board of Education for May 14, 2025
Washington Township Tables Decision on $11,000+ Security Upgrade, Seeks More Details
Washington Township Approves $2,500 in Sponsorships for Beecher EMS, July 4th Celebration
Washington Township to Continue Annual Senior Breakfast Amid Post-COVID Attendance Changes
Meeting Summary and Briefs: Washington Township Board of Trustees for May 5, 2025
County Approves $4.3 Million Purchase of Wetland Banking Credits for Highway Projects
Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for March 20, 2025
Beecher Fire District to Hire New Lieutenant, Approves Updated Appointment Process
Labor Representative Addresses County Committee on Public Transportation Reform Efforts
Committee Advances $1.7 Million Upgrade Plan for River Valley Juvenile Detention Center