Future regional power supply down, but not out

Future regional power supply down, but not out

Spread the love

(The Center Square) – Shrinking power supply remains a challenge according to the grid operator’s most recent capacity auction, signaling that regional utility bills could still climb, albeit more slowly, as demand for electricity grows faster than can be provided.

PJM, the organization tasked with managing the flow of power for 67 million people across 13 states and Washington, D.C., collects annual bids from generators that commit them to providing energy supply over the following 12 months. In this case, it’s for the 2028-29 operating year.

By doing so, the organization can better hedge against blackouts and soaring prices that could happen if there’s not enough power to turn on furnaces in the dead of winter or air conditioning at the height of summer.

“These auction results show that demand for electricity continues to grow faster than electricity supply,” said David Mills, PJM president and CEO. “At the same time, PJM recognizes how this supply-and-demand imbalance impacts the reliability of the system and costs for consumers. We are working with government and industry leaders on multiple fronts to restore that balance by bringing on new generation as fast as possible and managing the growth of new load on the grid.”

But a better solution, according to energy producers, state officials, and PJM alike, would be to plug more supply into the grid, which can help limit the stress fractures anticipated from the data center boom.

Auction Price

Results of PJM’s 2028-2029 Base Residual Auction show the price reached the federally approved cap of $325 per MW-day throughout the PJM region – 2.5% below the $333.44 price in the previous auction.

The auction’s cleared capacity totaled $16.4 billion. PJM notes that figure does not represent the total cost to customers because some utilities and other load-serving entities secure capacity through self-supply arrangements or bilateral contracts and are not subject to the auction clearing price.

Katie Blume, coalition chair of Clean Power PA, said the results amounted to “more of the same: high prices driven by surging data center demand, and a grid that’s getting less reliable, not more.”

Blume credited the price cap negotiated by Gov. Josh Shapiro with preventing steeper increases, saying it has saved consumers nearly $13 billion over two auctions. However, she said a cap does not add new power supplies or resolve PJM’s underlying problems.

She called for making data centers pay their “fair share” of grid costs and accelerating the connection of wind, solar, and battery-storage projects.

Reliability Shortfall

For the second consecutive auction, PJM secured less capacity than required to meet its reliability target. The 2028-2029 auction fell short by 6,831 MW, leaving the grid below the reserve cushion required to meet a one-in-10-year reliability standard.

A rough estimate puts the total number of homes powered by that many megawatts around 5.5 million. This figure assumes PJM’s standard of 1 MW is equal to supplying an average of 800 homes.

The organization, however, said that the shortfall does not necessarily mean the system will be unable to meet demand. It means the grid will operate with slimmer reserves and greater risk during extreme conditions. It continues to hold a reserve margin of 14.7%.

The shortfall was not unexpected given the trend. The previous auction fell approximately 6,500 MW short, and large load projects continue to be added to the demand forecast.

Forecast peak demand for 2028-2029 is approximately 2,000 MW higher than in the previous delivery year.

Supply and Proposed Solutions

The auction secured 138,318 MW of capacity, an increase of 3,733 MW from the previous auction. That included 525 MW from new generation and upgrades to existing plants.

That’s enough supply to power 69 million and 138 million homes, dependent upon the season.

The committed resources include: 46% natural gas, 20% nuclear, 18% coal, 5% demand response, 4% hydro, 2% wind, 2% oil, and 1% solar.

PJM said it is working to increase supply and manage demand by clearing its project queue, creating a faster pathway for certain high-priority generation proposals, improving the performance of existing plants, and developing “Connect and Manage” frameworks that would allow data centers and other large users to connect under flexible operating conditions.

The grid operator also plans to seek federal approval for a Reliability Backstop Procurement intended to address near-term supply needs.

“All of these initiatives are critical to keeping the lights on while allowing states to protect their everyday electricity customers,” Mills said.

Electric Power Supply Association President and CEO Todd Snitchler said historically low capacity prices had discouraged investment in generation, while the higher prices that began with PJM’s July 2024 auction prompted companies to announce, restart, expand, or advance tens of gigawatts of projects.

Snitchler said the immediate challenge is turning that investment into additional electricity supply by accelerating permitting, siting, and grid interconnection. He also cautioned against allowing utilities to finance new generation through mandatory customer charges, arguing that competitive suppliers and investors should continue to bear construction risks.

Claire Lang-Ree, advocate for climate and energy for the Natural Resources Defense Council said, the results confirm that data center growth is outpacing new electricity supply, weakening reliability, and keeping prices at the cap.

She called on PJM and state officials to ensure data centers pay for generation and transmission built to serve them and to accelerate the interconnection of lower-cost clean energy projects.

“The 67 million PJM residents literally can’t afford to suffer any more record-breaking auctions or near-blackout events,” Lang-Ree said.

PJM expects to submit its Reliability Backstop and Connect and Manage proposals to the Federal Energy Regulatory Commission in the coming weeks.

The next Base Residual Auction, for the 2029-2030 delivery year, is scheduled for December as PJM works to restore its three-year-ahead auction cycle.

Leave a Comment





Latest News Stories

solar panels photovoltaics in solar farm

Will County Braces for 6,000-Acre Solar Project; Prepare for ‘Massive’ Solar Hearings

Will County P&Z Commission Meeting | Jan. 20, 2026 Will County Braces for 6,000-Acre Solar Project; Commissioners Weigh Conflicts and Crowds Article Summary:The Will County Planning and Zoning Commission is...
Beecher Graphic.3

Beecher Board Updates Village Construction and Safety Codes

Village of Beecher Meeting | January 26, 2026 Article Summary: The Beecher Village Board has updated its building and safety regulations by adopting the 2021 International Code series. The new...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board for January 15, 2026

Will County Board Meeting | January 15, 2026 Meeting SummaryThe Will County Board met on January 15, 2026, to tackle a heavy agenda focused on infrastructure investment, legislative policy, and...
Police Crime

Pursuit following railroad theft ends in New Lenox; one suspect at large

NEW LENOX, Ill. – A reported cargo theft in Wilmington Township sparked a multi-jurisdictional pursuit Saturday morning that ended with a crash and a manhunt in a New Lenox neighborhood. The...
Will County Board Graphic.04

Waste Management Commits to Expanded Litter Patrols Around Landfill

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: Following complaints from county officials, Waste Management has agreed to significantly expand its litter collection efforts along roadways surrounding...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for Jan. 13, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, January 13, 2026, to continue its comprehensive update...
Will County Board Graphic.01

County Approves $22 Million in Road Projects for Lorenzo Road and Mills Road

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved major infrastructure contracts, including an $18.8 million bridge replacement on Lorenzo Road and a $3.2...
Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable...
Will County Board Graphic.03

Ad-Hoc Committee Retains Noise Ordinance Despite Enforcement Frustrations

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 Article Summary: The Ad-Hoc Ordinance Review Committee voted to retain the county’s public nuisance noise ordinance despite members describing...
Will County Board Graphic.03

Will County Commits $15M to Transfer Sanitary District Operations to City of Joliet

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board has authorized an intergovernmental agreement to dissolve the Southeast Joliet Sanitary District and transfer its water...
Beecher Elementary school Graphic

District 200-U Board Approves 2026-2027 Academic Calendar

Beecher School Board Meeting | Jan. 20, 2026 Article Summary: The Beecher School Board has officially set the schedule for the upcoming school year, approving the 2026-2027 calendar during a...
will county board meeting graphic.5

Prairie View Landfill Expansion Plans Take Shape as Consultants Navigate Design Challenges

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: Geologic Associates presented a detailed status update on the proposed expansion of the Prairie View Landfill, outlining a dual...
Will County Board Graphic.02

County Committee Proposes Federal Study on “Legacy Pollution” Near Joliet and Romeoville Refineries

Article Summary: In a draft lobbying platform presented to the Will County Board, the Legislative Committee outlined a request for a federal study to identify and mitigate health risks in...
beecher ilinois school board graphic.3

Beecher School Board Authorizes Dismissal of Tenured Employee

Beecher School Board Meeting | Jan. 20, 2026 Article Summary: The Beecher School District 200-U Board of Education voted Monday evening to authorize the dismissal of a tenured employee following...
will county board graphic

County Authorizes Condemnation to Advance Francis and Marley Road Improvements

Will County Board Meeting | January 15, 2026 Article Summary: To facilitate safety improvements at the intersection of Francis Road and Marley Road in New Lenox Township, the Will County...