Meeting Summary and Briefs: Beecher School District Facilities Committee for December 2025
Beecher School District Facilities Committee Meeting | December 2025
The Facilities Committee of the Beecher Board of Education met on Wednesday, December 3, 2025, to review capital projects and maintenance updates. The primary discussion centered on a major window and roof repair project for Beecher Elementary School to address persistent leaks. The committee leaned toward a proposal from GRP to replace windows and repair roof coping, targeting a January board vote.
Contractor Project Update:
Superintendent Dr. Jack Gaham noted that Mr. Hurley, a contractor, had been on-site earlier in the week but was delayed by cold weather. He is expected to return by the end of the week to finish outstanding work and address items at the Junior High.
Tuck Pointing Strategy:
The committee discussed the possibility of separating cosmetic or non-critical masonry repairs from the urgent water-intrusion project. Board members suggested that future tuck pointing needs could be bid out locally to Beecher-area masons to potentially save costs compared to bundling it with the specialized window and roofing contract.
Latest News Stories
Beecher High School to Get New Look with Approved Window Wrap
State’s Attorney Donates Tint Meters to Beecher Police to Enhance Traffic Safety
Brad Shrader Appointed to Fill Vacant Beecher School Board Seat
Beecher School Board Approves FY26 Budget With Projected Surplus, Earmarks Funds for Major Projects
Persistent Leaks at New Beecher Public Safety Facility Prompt Calls for Third-Party Inspection
Illinois’ gun ban set for oral arguments in appeals court Monday
Law professor explains why Trump could win tariff case
WATCH: Los Angeles schools superintendent renews contract
Southern California Edison works on paying Eaton Fire victims
U.S. Sen. Mark Kelly presents ‘AI for America’ roadmap
WATCH: Education department launches America 250 effort
Trump: Chicago needs ‘big, strong soldiers’