Beecher District Pushes Summer Roof, Window Projects Toward Fall Deadline

Spread the love

Beecher 200-U Board of Education Meeting | June 10, 2026

Article Summary: Beecher 200-U administrators told the board that roofing, window and floor projects are progressing across the elementary, junior high and high school buildings, with the elementary’s new second-floor windows expected to be finished by early July. The board declined to act on an $11,000 add-on parapet quote, directing staff to seek competing bids first.

Summer Construction Key Points:

  • New roofing and second-floor windows at Beecher Elementary are expected to wrap by late June or early July; floor restoration is underway at the junior high.
  • Work is being drawn from the district’s Health Life Safety fund, reported in the treasurer’s update at roughly $478,000.
  • The board held off on an $11,000 change order to cap a lower parapet section, asking staff to gather additional quotes.
  • Rain delayed the elementary roof start by two days, but crews were back on the roof the day of the meeting.

The update came during the superintendent’s report at the board’s regular meeting, held at 6 p.m. in the Beecher High School library. Superintendent Jack Gaham walked the board through projects that began almost immediately after the school year ended, framing them as Health Life Safety improvements — the category Illinois districts use for code, roofing and building-safety work.

Projects Across Three Buildings

At Beecher Elementary, a roofing contractor the district referred to as Langles had started the roofing and parapet work and was on site the day of the meeting, Gaham said. The crew got going two days late because of rain, but he estimated the roofing would take about two weeks, with new second-floor windows on roughly the same timeline.

“You should have a whole new second floor by the end of June, hopefully no later than early July,” Gaham told the board. He said the new windows would resemble the building’s lower-level units — a metal top section beneath the drop ceiling, the window itself, and sections that open. Gaham and Maintenance Director Nathan Stanula met with the roofing crew on the roof the prior Wednesday to review the scope.

At the junior high, crews had already completed door work and begun stripping floors down to the underlying tile ahead of re-waxing, which Gaham said Stanula expected to start on the athletic hallway the following week. “It’s unbelievable how many layers of wax,” the superintendent said, noting the floors had not been taken down to bare tile in roughly two decades. At the elementary, a closet door flagged by the fire marshal as an impermissible residential-style door was also upgraded, and two classrooms received new doors that did not require the heavier framing work needed elsewhere.

Board Holds Off on $11,000 Parapet Quote

Gaham also raised a possible add-on: while meeting with the project’s construction manager — referred to in the meeting as GRP — on the elementary roof, a representative named Jeremy offered to have the roofing company quote capping work on a lower parapet section. The figure came back at $11,000.

Gaham told the board he could not vouch for the number on its own. “I can’t tell you if this is a good number or a bad number,” he said, adding that Stanula was not especially concerned about the condition and that the work could be handled later by another vendor. Because the item would be a change order rather than a new contract, no vote was required; the board could simply authorize it. Members instead signaled they wanted competing quotes before committing, and Gaham said he would tell the contractor to proceed with the existing scope and revisit the parapet later.

The exact contract values for the larger roofing, window and flooring work were not read into the record at the meeting, and the treasurer’s report — which included the Health Life Safety fund balance — was delivered with several figures that were difficult to capture from the meeting audio. Gaham noted the Health Life Safety balance “will start going down with the project starting.”


Leave a Comment





Latest News Stories

beecher ilinois school board graphic.4

Beecher School Board Issues Suspension, Formal Notice to Remedy to Employee

Article Summary: The Beecher Board of Education has taken formal disciplinary action against district employee Jessica Carter, unanimously approving a resolution for an unpaid suspension and a "Third Issuance of...
beecher ilinois school board graphic.12

Dr. Marie Hansel Appointed to Fill Vacancy on Beecher School Board

Article Summary: Dr. Marie Hansel has been appointed to the Beecher Board of Education, filling a vacant seat on the seven-member board. Hansel took the official oath of office during...
beecher ilinois school board graphic.3

Beecher School Board Approves Amended Budget, New Staff Hires

Article Summary: The Beecher Board of Education unanimously approved the Fiscal Year 2025 amended budget following a brief public hearing with no comment from the public. The board also approved...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Board of Education for May 14, 2025

The Beecher Board of Education appointed a new member, approved over $88,000 in major infrastructure repairs for the high school, and took formal disciplinary action against an employee during its...
washington township graphic.1

Washington Township Tables Decision on $11,000+ Security Upgrade, Seeks More Details

Article Summary: The Washington Township Board of Trustees has deferred a decision on a significant security system overhaul, citing the need to clarify key differences between two bids from TK...
washington township graphic.2

Washington Township Approves $2,500 in Sponsorships for Beecher EMS, July 4th Celebration

Article Summary: The Washington Township Board unanimously approved two community sponsorships totaling $2,500, continuing its financial support for the Village of Beecher's Emergency Management Agency (EMA) and the annual 4th...
washington township graphic.3

Washington Township to Continue Annual Senior Breakfast Amid Post-COVID Attendance Changes

Article Summary: Following a discussion about lower-than-historic attendance at its recent Senior Breakfast, the Washington Township Board decided to maintain one breakfast event per year. The board concluded that the...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for May 5, 2025

The Washington Township Board of Trustees paused a decision on a major security upgrade, approved community sponsorships, and discussed the future of its senior events at its meeting on Monday,...
Screenshot 2025-05-04 at 3.03.49 PM

County Approves $4.3 Million Purchase of Wetland Banking Credits for Highway Projects

The Will County Public Works and Transportation Committee has approved an agreement to purchase wetland banking site credits for $4,324,550 from V3 Wetland Restoration LLC to support future county highway...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for March 20, 2025

The Beecher Fire Protection District is preparing for changes in its leadership and staffing after the Board of Trustees on March 20 approved the creation of a new Lieutenant position....
Beecher Fire Protection District graphic.1

Beecher Fire District to Hire New Lieutenant, Approves Updated Appointment Process

Article Summary: The Beecher Fire Protection District Board of Trustees has authorized the creation of a new Lieutenant position and will begin accepting applications at the end of March. The...
Screenshot 2025-05-04 at 2.01.41 PM

Labor Representative Addresses County Committee on Public Transportation Reform Efforts

JOLIET — A labor representative warned Will County officials Thursday that proposed reforms to regional public transportation governance could diminish the county's voice in transit decisions during a presentation to...
Screenshot 2025-05-04 at 2.01.41 PM

Committee Advances $1.7 Million Upgrade Plan for River Valley Juvenile Detention Center

JOLIET — The Will County Executive Committee voted Thursday to advance a $1.7 million proposal to upgrade the River Valley Juvenile Detention Center rather than pursuing costlier alternatives to house...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Briefs: Transportation Program Expands, Ordinances Updated

Mobility Management Program Expands to Three Townships: The Executive Committee approved an intergovernmental agreement to expand the Will County Mobility Management Program to include Channahon, Manhattan, and Plainfield townships. The...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Advances Elected Officials’ Pay Increases After Extended Debate

The Will County Executive Committee voted Thursday to advance a proposal for pay increases for countywide elected officials and county board members, setting the stage for a final vote at...