Beecher District Pushes Summer Roof, Window Projects Toward Fall Deadline

Spread the love

Beecher 200-U Board of Education Meeting | June 10, 2026

Article Summary: Beecher 200-U administrators told the board that roofing, window and floor projects are progressing across the elementary, junior high and high school buildings, with the elementary’s new second-floor windows expected to be finished by early July. The board declined to act on an $11,000 add-on parapet quote, directing staff to seek competing bids first.

Summer Construction Key Points:

  • New roofing and second-floor windows at Beecher Elementary are expected to wrap by late June or early July; floor restoration is underway at the junior high.
  • Work is being drawn from the district’s Health Life Safety fund, reported in the treasurer’s update at roughly $478,000.
  • The board held off on an $11,000 change order to cap a lower parapet section, asking staff to gather additional quotes.
  • Rain delayed the elementary roof start by two days, but crews were back on the roof the day of the meeting.

The update came during the superintendent’s report at the board’s regular meeting, held at 6 p.m. in the Beecher High School library. Superintendent Jack Gaham walked the board through projects that began almost immediately after the school year ended, framing them as Health Life Safety improvements — the category Illinois districts use for code, roofing and building-safety work.

Projects Across Three Buildings

At Beecher Elementary, a roofing contractor the district referred to as Langles had started the roofing and parapet work and was on site the day of the meeting, Gaham said. The crew got going two days late because of rain, but he estimated the roofing would take about two weeks, with new second-floor windows on roughly the same timeline.

“You should have a whole new second floor by the end of June, hopefully no later than early July,” Gaham told the board. He said the new windows would resemble the building’s lower-level units — a metal top section beneath the drop ceiling, the window itself, and sections that open. Gaham and Maintenance Director Nathan Stanula met with the roofing crew on the roof the prior Wednesday to review the scope.

At the junior high, crews had already completed door work and begun stripping floors down to the underlying tile ahead of re-waxing, which Gaham said Stanula expected to start on the athletic hallway the following week. “It’s unbelievable how many layers of wax,” the superintendent said, noting the floors had not been taken down to bare tile in roughly two decades. At the elementary, a closet door flagged by the fire marshal as an impermissible residential-style door was also upgraded, and two classrooms received new doors that did not require the heavier framing work needed elsewhere.

Board Holds Off on $11,000 Parapet Quote

Gaham also raised a possible add-on: while meeting with the project’s construction manager — referred to in the meeting as GRP — on the elementary roof, a representative named Jeremy offered to have the roofing company quote capping work on a lower parapet section. The figure came back at $11,000.

Gaham told the board he could not vouch for the number on its own. “I can’t tell you if this is a good number or a bad number,” he said, adding that Stanula was not especially concerned about the condition and that the work could be handled later by another vendor. Because the item would be a change order rather than a new contract, no vote was required; the board could simply authorize it. Members instead signaled they wanted competing quotes before committing, and Gaham said he would tell the contractor to proceed with the existing scope and revisit the parapet later.

The exact contract values for the larger roofing, window and flooring work were not read into the record at the meeting, and the treasurer’s report — which included the Health Life Safety fund balance — was delivered with several figures that were difficult to capture from the meeting audio. Gaham noted the Health Life Safety balance “will start going down with the project starting.”


Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 2.08.10 PM

Will County Considers Relaxing Size Restrictions on Accessory Dwelling Units

JOLIET — Will County officials are considering revisions to zoning regulations that would allow larger accessory dwelling units (ADUs), potentially expanding housing options in the county while addressing concerns about...
Screenshot 2025-05-04 at 2.08.10 PM

Resident Urges County to Restrict Residential Motocross Tracks After Neighborhood Dispute

JOLIET — A Will County resident appeared before the Land Use and Development Committee Thursday urging officials to modify zoning codes to prohibit motocross tracks in residential neighborhoods, citing an...
Screenshot 2025-05-04 at 2.08.10 PM

Committee Approves Truck Terminal Special Use Permit After Safety Modifications

JOLIET — The Will County Land Use and Development Committee voted Thursday to approve a special use permit for a truck terminal in New Lenox Township, after the applicant made...
Screenshot 2025-05-04 at 2.08.10 PM

County Committee Approves Two Solar Energy Projects Despite Farmland Concerns

JOLIET — The Will County Land Use and Development Committee approved two commercial solar energy projects Thursday, advancing the proposals to the full county board for final consideration despite concerns...
Screenshot 2025-05-04 at 3.03.49 PM

Will County Approves Vision Zero Initiative to Reduce Traffic Fatalities

Will County has officially adopted Vision Zero, a data-driven safety initiative aimed at eliminating traffic fatalities throughout the county. The Public Works and Transportation Committee unanimously approved the resolution, which...
Screenshot 2025-05-04 at 3.03.49 PM

County’s First Roundabout Planned for Exchange Street and Beecher Road Intersection

Will County's first roundabout is advancing to the final public meeting phase, with construction tentatively scheduled for 2027. County Engineer Jeff Ronaldson announced that the Department of Transportation will hold...
Screenshot 2025-05-04 at 3.03.49 PM

County Accepts $377,000 Developer Donation for Romeo Road Improvements

The Will County Public Works and Transportation Committee has accepted a $377,000 donation from a developer to fund roadway improvements at the southeast corner of Romeo Road and Weber Road...
Screenshot 2025-05-04 at 3.03.49 PM

Contracts Awarded for LED Signal Upgrades and Guardrail Maintenance

The Will County Public Works and Transportation Committee has approved contracts for two significant infrastructure maintenance projects: LED traffic signal upgrades and guardrail maintenance across the county. A contract for...
Screenshot 2025-05-04 at 3.03.49 PM

BRIEFS: Will County Public Works Projects

County Line Road Resurfacing Contract Awarded: The committee approved a $767,249 contract to Iroquois Paving Corporation for resurfacing County Highway 58 (County Line Road) from N5000 East Road east to...
Screenshot 2025-05-04 at 2.36.35 PM

County Approves Two Solar Energy Projects, Committee Discusses Zoning Challenges

The Will County Land Use and Development Committee approved two commercial solar energy projects Wednesday despite objections from the Village of Manhattan regarding one of the proposals. In a 6-1...
Screenshot 2025-05-04 at 2.36.35 PM

Committee Debates Easing Size Restrictions on Accessory Dwelling Units

Will County's Land Use and Development Committee is considering changes to its accessory dwelling unit (ADU) regulations that could provide more flexibility for homeowners looking to create additional living spaces...
Screenshot 2025-05-04 at 2.36.35 PM

“Tiny Homes” Status Creates Regulatory Confusion for County Officials

Will County officials are struggling to establish clear regulations for "tiny homes," with committee members expressing confusion over terminology and appropriate standards during Wednesday's Land Use and Development Committee meeting....
Screenshot 2025-05-04 at 2.36.35 PM

County Officials Begin Exploring Regulations for Small Modular Nuclear Reactors

Will County is beginning to explore potential regulations for small modular nuclear reactors (SMRs) after recent Illinois legislation allowed their development, planning staff told the Land Use and Development Committee...
Screenshot 2025-05-04 at 2.17.47 PM

Will County Land Use News Briefs

Truck Terminal Proposal Tabled for Traffic Study: The committee tabled a special use permit request from Litmax Multi-Service Inc. for a truck terminal in New Lenox Township at 22645 Cherry...
Screenshot 2025-05-04 at 2.57.14 PM

County Moves Forward with Veterans Building Renovations, Questions Arise on Pace Building Plans

Will County's Capital Improvements Committee received updates Tuesday on multiple county facility projects, including progress on the Copperfield Drive building renovations for veterans services, while discussions revealed questions about the...