Beecher Elementary school Graphic

Beecher District Pushes Summer Roof, Window Projects Toward Fall Deadline

Spread the love

Beecher 200-U Board of Education Meeting | June 10, 2026

Article Summary: Beecher 200-U administrators told the board that roofing, window and floor projects are progressing across the elementary, junior high and high school buildings, with the elementary’s new second-floor windows expected to be finished by early July. The board declined to act on an $11,000 add-on parapet quote, directing staff to seek competing bids first.

Summer Construction Key Points:

  • New roofing and second-floor windows at Beecher Elementary are expected to wrap by late June or early July; floor restoration is underway at the junior high.
  • Work is being drawn from the district’s Health Life Safety fund, reported in the treasurer’s update at roughly $478,000.
  • The board held off on an $11,000 change order to cap a lower parapet section, asking staff to gather additional quotes.
  • Rain delayed the elementary roof start by two days, but crews were back on the roof the day of the meeting.

The update came during the superintendent’s report at the board’s regular meeting, held at 6 p.m. in the Beecher High School library. Superintendent Jack Gaham walked the board through projects that began almost immediately after the school year ended, framing them as Health Life Safety improvements — the category Illinois districts use for code, roofing and building-safety work.

Projects Across Three Buildings

At Beecher Elementary, a roofing contractor the district referred to as Langles had started the roofing and parapet work and was on site the day of the meeting, Gaham said. The crew got going two days late because of rain, but he estimated the roofing would take about two weeks, with new second-floor windows on roughly the same timeline.

“You should have a whole new second floor by the end of June, hopefully no later than early July,” Gaham told the board. He said the new windows would resemble the building’s lower-level units — a metal top section beneath the drop ceiling, the window itself, and sections that open. Gaham and Maintenance Director Nathan Stanula met with the roofing crew on the roof the prior Wednesday to review the scope.

At the junior high, crews had already completed door work and begun stripping floors down to the underlying tile ahead of re-waxing, which Gaham said Stanula expected to start on the athletic hallway the following week. “It’s unbelievable how many layers of wax,” the superintendent said, noting the floors had not been taken down to bare tile in roughly two decades. At the elementary, a closet door flagged by the fire marshal as an impermissible residential-style door was also upgraded, and two classrooms received new doors that did not require the heavier framing work needed elsewhere.

Board Holds Off on $11,000 Parapet Quote

Gaham also raised a possible add-on: while meeting with the project’s construction manager — referred to in the meeting as GRP — on the elementary roof, a representative named Jeremy offered to have the roofing company quote capping work on a lower parapet section. The figure came back at $11,000.

Gaham told the board he could not vouch for the number on its own. “I can’t tell you if this is a good number or a bad number,” he said, adding that Stanula was not especially concerned about the condition and that the work could be handled later by another vendor. Because the item would be a change order rather than a new contract, no vote was required; the board could simply authorize it. Members instead signaled they wanted competing quotes before committing, and Gaham said he would tell the contractor to proceed with the existing scope and revisit the parapet later.

The exact contract values for the larger roofing, window and flooring work were not read into the record at the meeting, and the treasurer’s report — which included the Health Life Safety fund balance — was delivered with several figures that were difficult to capture from the meeting audio. Gaham noted the Health Life Safety balance “will start going down with the project starting.”


Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 2.01.41 PM

County Considers Bond Refinancing That Could Save Millions

JOLIET — Will County officials on Thursday discussed a potential bond refinancing opportunity that could save the county approximately $3.6 million in debt service costs by taking advantage of favorable...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Briefs: Unanimous Votes for Proclamations, Title Changes, Audits Discussed

Committee Clarifies Unanimous Vote Requirement for Honorary Proclamations: The Ordinance Committee refined language in Chapter 30 regarding honorary proclamations, specifying that they shall be allowed "only by unanimous vote" of...
Screenshot 2025-05-04 at 2.14.20 PM

County Undertakes Formatting Overhaul of Decades-Old Ordinances

JOLIET — Will County officials are modernizing the format and structure of the county's ordinances, some of which date back to 1943, as part of a comprehensive review process to...
Screenshot 2025-05-04 at 2.14.20 PM

County Reviews Rules on Virtual Meeting Attendance, Committee Participation

JOLIET — Will County officials discovered Thursday that their current practices regarding virtual meeting attendance may not fully comply with state law, as the Ordinance Committee worked through updates to...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Reviews Administrative Code, Clarifies Official Powers

JOLIET — The Will County Ordinance Committee spent several hours Thursday reviewing and updating Chapter 30 of the county's Code of Ordinances, which governs county administration, with particular attention to...
Screenshot 2025-05-04 at 2.17.47 PM

Farmers, Residents Call for Action on Roadside Debris from Landfill Trucks

Local farmers and residents are urging county officials to address persistent litter problems along routes used by trucks traveling to and from Prairie View landfill. The issue emerged during public...
Screenshot 2025-05-04 at 2.17.47 PM

County Landfill Meeting Briefs

Landfill Minutes Approved: The landfill committee unanimously approved minutes from its February 11, 2025 meeting. All committee members were present, including Hickey, Brooks, Bulock, Logan, Newquest, Pretzel, and Dean Schlotman....
Screenshot 2025-05-04 at 2.17.47 PM

Geological Features Central to Landfill Expansion Plans

Geological characteristics that were formed thousands of years ago make Prairie View an ideal location for landfill operations, according to the geologist leading expansion plans for the facility. During Wednesday's...
Screenshot 2025-05-04 at 2.17.47 PM

County Considers Two Options for Prairie View Landfill Expansion

Prairie View landfill could extend its lifespan by up to 35 additional years under expansion plans presented to the county's landfill committee on Wednesday. Consultant Marty Fallon outlined two potential...
Screenshot 2025-05-04 at 2.24.10 PM

Health Department Faces Funding Cuts, Reviews Options for Programs

The Will County Health Department is assessing its options after being notified of the termination of a $1 million federal grant for respiratory disease surveillance and outbreak response, officials told...
Screenshot 2025-05-04 at 2.24.10 PM

County Health News Briefs

Sunny Hill Nursing Home Reports Full Capacity: The county-owned Sunny Hill Nursing Home is operating at 100% capacity with all 156 beds filled and a waiting list, Administrator Maggie McDall...
Screenshot 2025-05-04 at 2.24.10 PM

Substance Use Initiative Reports Early 2025 Overdose Data, Outreach Efforts

Will County has recorded eight fatal overdoses and seven overdose reversals so far in 2025, according to data presented to the county health committee on Wednesday. Connie Dewal, program manager...
Screenshot 2025-05-04 at 2.24.10 PM

County Food Access Program Reports Progress on ARPA-Funded Initiatives

Four community organizations are expanding food assistance services across Will County through nearly $80,000 in federal American Rescue Plan Act (ARPA) funds administered by the county's food access collaborative. Caitlyn...
Screenshot 2025-05-04 at 2.24.10 PM

Sunny Hill Nursing Home Reaches Full Capacity, Completes Bed Upgrades

Will County's Sunny Hill Nursing Home is operating at 100% capacity with a waiting list for admissions, prompting officials to consider reinstating a policy that would prioritize county residents, Administrator...
Screenshot 2025-05-04 at 2.08.10 PM

Will County Land Use and Development Briefs: Minor Subdivision, Extension Approved, Tiny Homes Advocate Returns

Committee Approves Minor Subdivision to Correct Illegal Land Division: The Land Use and Development Committee unanimously approved a minor subdivision plat for the Crown Holm Family Trust in Lockport Township,...